Deal: St. Louis Park West End, 200 unitsPage: Total project cost

Total project cost

Sample

Every dollar of the budget, line by line, per unit and per gross SF.Model v1, worked example, no edits

Sample deal. Lines are the worked example's stated budget; edits save in this browser.

Total project cost
$52,189,000
$260,945 per unit, $164.35 per gross SF
Land · of total
3.8%
$2,000,000, $10,000 per unit
Hard costs · of total
79.5%
$41,488,510, $207,443 per unit, with contingency
Soft and other costs · of total
16.7%
$8,700,490, $43,502 per unit. Soft, developer fee and financing.
  • Land$2,000,0003.8%
  • Hard costs$41,488,51079.5%
  • Soft costs$4,212,7738.1%
  • Developer fee$2,040,0003.9%
  • Financing$2,447,7174.7%

Total project cost$52,189,000100.0%

The budget, line by line

The pro forma's Budget tab, line by line. Select the pencil beside an amount to change it; open hard costs for the leveled bid by trade.

Land$2,000,000

  • Land$2,000,000

    3.8% of total, $10,000 per unit, $6.30 per GSF

    Month 0, at closing.Model

  • Subtotal, land$2,000,0003.8%, $10,000 per unit, $6.30 per GSF

Hard costs$41,488,510

  • $41,000,000

    78.6% of total, $205,000 per unit, $129.12 per GSF

    Over construction, back-loaded. Open for the leveled bid by trade.Model

  • Hard cost contingency$488,510

    0.9% of total, $2,443 per unit, $1.54 per GSF

    Months 8 to 24.Model

  • Subtotal, hard costs$41,488,51079.5%, $207,443 per unit, $130.65 per GSF

Soft costs$4,212,773

  • Architecture & engineering$1,221,000

    2.3% of total, $6,105 per unit, $3.85 per GSF

    Months 1 to 8.Model

  • $1,600,000

    3.1% of total, $8,000 per unit, $5.04 per GSF

    Months 1 to 6.Model

    City fees

  • Legal, title, closing$212,403

    0.4% of total, $1,062 per unit, $0.67 per GSF

    Month 0, at closing.Model

  • Title and closing$163,855

    0.3% of total, $819 per unit, $0.52 per GSF

    Month 0, at closing.Model

  • Marketing & lease-up costs$250,000

    0.5% of total, $1,250 per unit, $0.79 per GSF

    Months 18 to 24.Model

  • FF&E / amenities$375,000

    0.7% of total, $1,875 per unit, $1.18 per GSF

    Months 18 to 24.Model

  • Taxes & insurance during construction$289,648

    0.6% of total, $1,448 per unit, $0.91 per GSF

    Months 20 to 24.Model

  • Operating / lease-up reserve$100,868

    0.2% of total, $504 per unit, $0.32 per GSF

    Held for lease-up.Model

  • Subtotal, soft costs$4,212,7738.1%, $21,064 per unit, $13.27 per GSF

Developer fee$2,040,000

  • Developer fee$2,040,000

    3.9% of total, $10,200 per unit, $6.42 per GSF

    Over construction.Model

  • Subtotal, developer fee$2,040,0003.9%, $10,200 per unit, $6.42 per GSF

Financing$2,447,717

  • Interest reserve (budgeted)$2,193,302

    4.2% of total, $10,967 per unit, $6.91 per GSF

    Capitalized through month 24.Model

  • Construction loan origination fee$254,415

    0.5% of total, $1,272 per unit, $0.80 per GSF

    Month 0, at closing.Model

  • Subtotal, financing$2,447,7174.7%, $12,239 per unit, $7.71 per GSF

Total project cost$52,189,000100.0%, $260,945 per unit, $164.35 per GSF

Where the detail lines come from
  • Lines and names follow the pro forma's Budget tab. Model: the worked example's stated line. Entered: a value saved in this browser.
  • Hard costs are one total. Opening the line shows it split in the proportions of the low leveled bid, Prairie Contractors, whose comparable total is $44,092,922 ($3,092,922 over the line).
  • St. Louis Park fee rows on this building come to $1,080,600; the rest of the model's $1,600,000 line is not itemized.
  • Title and closing, marketing, FF&E and the origination fee split uses-table lines by stated sample shares; see the model reconciliation.
  • Per gross SF on 317,543 gross SF, the building program's area for 4 over 1.

Sources and uses

Both sides tie to the model's total project cost.

  • Equity

    Amount
    $18,266,779
    Of total
    35.0%
  • Construction loan

    65.0% loan to cost, stated

    Amount
    $33,922,000
    Of total
    65.0%
  • TIF and grants

    None in the model

    Amount
    $0
    Of total
    0.0%
  • Unfunded, model rounding seam

    Stated equity plus loan against stated cost

    Amount
    $221
    Of total
    0.0%
  • Total sources

    Amount
    $52,189,000
    Of total
    100.0%
  • Land

    Amount
    $2,000,000
    Of total
    3.8%
  • Hard costs

    Amount
    $41,488,510
    Of total
    79.5%
  • Soft costs

    Amount
    $4,212,773
    Of total
    8.1%
  • Developer fee

    Amount
    $2,040,000
    Of total
    3.9%
  • Financing

    Amount
    $2,447,717
    Of total
    4.7%
  • Total uses

    Amount
    $52,189,000
    Of total
    100.0%