Total project cost
SampleEvery dollar of the budget, line by line, per unit and per gross SF.Model v1, worked example, no edits
Sample deal. Lines are the worked example's stated budget; edits save in this browser.
Edit budget: Total project cost
Model v1, worked example, no edits
- Total project cost
- $52,189,000
- $260,945 per unit, $164.35 per gross SF
- Land · of total
- 3.8%
- $2,000,000, $10,000 per unit
- Hard costs · of total
- 79.5%
- $41,488,510, $207,443 per unit, with contingency
- Soft and other costs · of total
- 16.7%
- $8,700,490, $43,502 per unit. Soft, developer fee and financing.
- Land$2,000,0003.8%
- Hard costs$41,488,51079.5%
- Soft costs$4,212,7738.1%
- Developer fee$2,040,0003.9%
- Financing$2,447,7174.7%
Total project cost$52,189,000100.0%
The budget, line by line
The pro forma's Budget tab, line by line. Select the pencil beside an amount to change it; open hard costs for the leveled bid by trade.
Land$2,000,000
- Land$2,000,000
3.8% of total, $10,000 per unit, $6.30 per GSF
Month 0, at closing.Model
- Subtotal, land$2,000,0003.8%, $10,000 per unit, $6.30 per GSF
Hard costs$41,488,510
- $41,000,000
78.6% of total, $205,000 per unit, $129.12 per GSF
Over construction, back-loaded. Open for the leveled bid by trade.Model
- Sitework$1,225,8492.3%, $6,129 per unit, $3.86 per GSF, Leveled bid split, Div 31, 32, 33
- Concrete$5,427,11510.4%, $27,136 per unit, $17.09 per GSF, Leveled bid split, Div 03, 04
- Framing and carpentry$7,060,78013.5%, $35,304 per unit, $22.24 per GSF, Leveled bid split, Div 05, 06
- Roofing and envelope$3,757,2487.2%, $18,786 per unit, $11.83 per GSF, Leveled bid split, Div 07
- Doors and windows$2,066,0644.0%, $10,330 per unit, $6.51 per GSF, Leveled bid split, Div 08
- Finishes$5,050,0269.7%, $25,250 per unit, $15.90 per GSF, Leveled bid split, Div 09
- Specialties, equipment and elevators$1,810,2543.5%, $9,051 per unit, $5.70 per GSF, Leveled bid split, Div 10, 11, 12; Div 14
- MEP: plumbing, HVAC and electrical$10,133,94919.4%, $50,670 per unit, $31.91 per GSF, Leveled bid split, Div 21, 22; Div 23; Div 26, 27, 28
- General conditions$2,454,3874.7%, $12,272 per unit, $7.73 per GSF, Leveled bid split, Div 01
- Contractor fee, insurance and bond$2,014,3283.9%, $10,072 per unit, $6.34 per GSF, Leveled bid split, No CSI division
- Hard cost contingency$488,510
0.9% of total, $2,443 per unit, $1.54 per GSF
Months 8 to 24.Model
- Subtotal, hard costs$41,488,51079.5%, $207,443 per unit, $130.65 per GSF
Soft costs$4,212,773
- Architecture & engineering$1,221,000
2.3% of total, $6,105 per unit, $3.85 per GSF
Months 1 to 8.Model
- $1,600,000
3.1% of total, $8,000 per unit, $5.04 per GSF
Months 1 to 6.Model
- SAC (sewer availability charge)$397,6000.8%, $1,988 per unit, $1.25 per GSF, City fees, Met Council, published schedule
- WAC (water availability charge)$128,0000.2%, $640 per unit, $0.40 per GSF, City fees, City, published schedule
- Park dedication$300,0000.6%, $1,500 per unit, $0.94 per GSF, City fees, City, published schedule
- Trunk area charge$20,0000.0%, $100 per unit, $0.06 per GSF, City fees, City, sample
- Building permit$190,0000.4%, $950 per unit, $0.60 per GSF, City fees, City, sample
- Plan review$45,0000.1%, $225 per unit, $0.14 per GSF, City fees, City, sample
- Other city and government, not itemized$519,4001.0%, $2,597 per unit, $1.64 per GSF, Model remainder
- Legal, title, closing$212,403
0.4% of total, $1,062 per unit, $0.67 per GSF
Month 0, at closing.Model
- Title and closing$163,855
0.3% of total, $819 per unit, $0.52 per GSF
Month 0, at closing.Model
- Marketing & lease-up costs$250,000
0.5% of total, $1,250 per unit, $0.79 per GSF
Months 18 to 24.Model
- FF&E / amenities$375,000
0.7% of total, $1,875 per unit, $1.18 per GSF
Months 18 to 24.Model
- Taxes & insurance during construction$289,648
0.6% of total, $1,448 per unit, $0.91 per GSF
Months 20 to 24.Model
- Operating / lease-up reserve$100,868
0.2% of total, $504 per unit, $0.32 per GSF
Held for lease-up.Model
- Subtotal, soft costs$4,212,7738.1%, $21,064 per unit, $13.27 per GSF
Developer fee$2,040,000
- Developer fee$2,040,000
3.9% of total, $10,200 per unit, $6.42 per GSF
Over construction.Model
- Subtotal, developer fee$2,040,0003.9%, $10,200 per unit, $6.42 per GSF
Financing$2,447,717
- Interest reserve (budgeted)$2,193,302
4.2% of total, $10,967 per unit, $6.91 per GSF
Capitalized through month 24.Model
- Construction loan origination fee$254,415
0.5% of total, $1,272 per unit, $0.80 per GSF
Month 0, at closing.Model
- Subtotal, financing$2,447,7174.7%, $12,239 per unit, $7.71 per GSF
Total project cost$52,189,000100.0%, $260,945 per unit, $164.35 per GSF
| Line | Amount | Per unit | Per GSF | Of total | Source |
|---|---|---|---|---|---|
| Land | |||||
| LandMonth 0, at closing | $2,000,000 | $10,000 | $6.30 | 3.8% | Model |
| Subtotal, land | $2,000,000 | $10,000 | $6.30 | 3.8% | |
| Hard costs | |||||
| Over construction, back-loaded. Open for the leveled bid by trade | $41,000,000 | $205,000 | $129.12 | 78.6% | Model |
| SiteworkDiv 31, 32, 33 | $1,225,849 | $6,129 | $3.86 | 2.3% | Leveled bid split |
| ConcreteDiv 03, 04 | $5,427,115 | $27,136 | $17.09 | 10.4% | Leveled bid split |
| Framing and carpentryDiv 05, 06 | $7,060,780 | $35,304 | $22.24 | 13.5% | Leveled bid split |
| Roofing and envelopeDiv 07 | $3,757,248 | $18,786 | $11.83 | 7.2% | Leveled bid split |
| Doors and windowsDiv 08 | $2,066,064 | $10,330 | $6.51 | 4.0% | Leveled bid split |
| FinishesDiv 09 | $5,050,026 | $25,250 | $15.90 | 9.7% | Leveled bid split |
| Specialties, equipment and elevatorsDiv 10, 11, 12; Div 14 | $1,810,254 | $9,051 | $5.70 | 3.5% | Leveled bid split |
| MEP: plumbing, HVAC and electricalDiv 21, 22; Div 23; Div 26, 27, 28 | $10,133,949 | $50,670 | $31.91 | 19.4% | Leveled bid split |
| General conditionsDiv 01 | $2,454,387 | $12,272 | $7.73 | 4.7% | Leveled bid split |
| Contractor fee, insurance and bondNo CSI division | $2,014,328 | $10,072 | $6.34 | 3.9% | Leveled bid split |
| Hard cost contingencyMonths 8 to 24 | $488,510 | $2,443 | $1.54 | 0.9% | Model |
| Subtotal, hard costs | $41,488,510 | $207,443 | $130.65 | 79.5% | |
| Soft costs | |||||
| Architecture & engineeringMonths 1 to 8 | $1,221,000 | $6,105 | $3.85 | 2.3% | Model |
| Months 1 to 6. City fees | $1,600,000 | $8,000 | $5.04 | 3.1% | Model |
| SAC (sewer availability charge)Met Council, published schedule | $397,600 | $1,988 | $1.25 | 0.8% | City fees |
| WAC (water availability charge)City, published schedule | $128,000 | $640 | $0.40 | 0.2% | City fees |
| Park dedicationCity, published schedule | $300,000 | $1,500 | $0.94 | 0.6% | City fees |
| Trunk area chargeCity, sample | $20,000 | $100 | $0.06 | 0.0% | City fees |
| Building permitCity, sample | $190,000 | $950 | $0.60 | 0.4% | City fees |
| Plan reviewCity, sample | $45,000 | $225 | $0.14 | 0.1% | City fees |
| Other city and government, not itemized | $519,400 | $2,597 | $1.64 | 1.0% | Model remainder |
| Legal, title, closingMonth 0, at closing | $212,403 | $1,062 | $0.67 | 0.4% | Model |
| Title and closingMonth 0, at closing | $163,855 | $819 | $0.52 | 0.3% | Model |
| Marketing & lease-up costsMonths 18 to 24 | $250,000 | $1,250 | $0.79 | 0.5% | Model |
| FF&E / amenitiesMonths 18 to 24 | $375,000 | $1,875 | $1.18 | 0.7% | Model |
| Taxes & insurance during constructionMonths 20 to 24 | $289,648 | $1,448 | $0.91 | 0.6% | Model |
| Operating / lease-up reserveHeld for lease-up | $100,868 | $504 | $0.32 | 0.2% | Model |
| Subtotal, soft costs | $4,212,773 | $21,064 | $13.27 | 8.1% | |
| Developer fee | |||||
| Developer feeOver construction | $2,040,000 | $10,200 | $6.42 | 3.9% | Model |
| Subtotal, developer fee | $2,040,000 | $10,200 | $6.42 | 3.9% | |
| Financing | |||||
| Interest reserve (budgeted)Capitalized through month 24 | $2,193,302 | $10,967 | $6.91 | 4.2% | Model |
| Construction loan origination feeMonth 0, at closing | $254,415 | $1,272 | $0.80 | 0.5% | Model |
| Subtotal, financing | $2,447,717 | $12,239 | $7.71 | 4.7% | |
| Total project cost | $52,189,000 | $260,945 | $164.35 | 100.0% | Model |
Where the detail lines come from
- Lines and names follow the pro forma's Budget tab. Model: the worked example's stated line. Entered: a value saved in this browser.
- Hard costs are one total. Opening the line shows it split in the proportions of the low leveled bid, Prairie Contractors, whose comparable total is $44,092,922 ($3,092,922 over the line).
- St. Louis Park fee rows on this building come to $1,080,600; the rest of the model's $1,600,000 line is not itemized.
- Title and closing, marketing, FF&E and the origination fee split uses-table lines by stated sample shares; see the model reconciliation.
- Per gross SF on 317,543 gross SF, the building program's area for 4 over 1.
Sources and uses
Both sides tie to the model's total project cost.
Equity
- Amount
- $18,266,779
- Of total
- 35.0%
Construction loan
65.0% loan to cost, stated
- Amount
- $33,922,000
- Of total
- 65.0%
TIF and grants
None in the model
- Amount
- $0
- Of total
- 0.0%
Unfunded, model rounding seam
Stated equity plus loan against stated cost
- Amount
- $221
- Of total
- 0.0%
Total sources
- Amount
- $52,189,000
- Of total
- 100.0%
| Sources | Amount | Of total |
|---|---|---|
| Equity | $18,266,779 | 35.0% |
| Construction loan65.0% loan to cost, stated | $33,922,000 | 65.0% |
| TIF and grantsNone in the model | $0 | 0.0% |
| Unfunded, model rounding seamStated equity plus loan against stated cost | $221 | 0.0% |
| Total sources | $52,189,000 | 100.0% |
Land
- Amount
- $2,000,000
- Of total
- 3.8%
Hard costs
- Amount
- $41,488,510
- Of total
- 79.5%
Soft costs
- Amount
- $4,212,773
- Of total
- 8.1%
Developer fee
- Amount
- $2,040,000
- Of total
- 3.9%
Financing
- Amount
- $2,447,717
- Of total
- 4.7%
Total uses
- Amount
- $52,189,000
- Of total
- 100.0%
| Uses | Amount | Of total |
|---|---|---|
| Land | $2,000,000 | 3.8% |
| Hard costs | $41,488,510 | 79.5% |
| Soft costs | $4,212,773 | 8.1% |
| Developer fee | $2,040,000 | 3.9% |
| Financing | $2,447,717 | 4.7% |
| Total uses | $52,189,000 | 100.0% |