Which bid is lowest once leveled
Face bid plus leveling, against the hard cost budget. Select a bid for its panel.
Leveling, bidders and the package
| Line | BudgetSample split | |||||
|---|---|---|---|---|---|---|
| Base bid by division | ||||||
| Sitework | $2,151,600 | $2,184,900 | Excl.$2,228,700Plug, not the bidder's number | $2,262,500 | $2,351,200 | $2,050,000 |
| Concrete | $5,651,800 | $5,651,800 | $5,709,500 | $5,824,800 | $6,055,500 | $5,330,000 |
| Framing and carpentry | $7,353,100 | $7,466,200 | $7,428,500 | $7,767,900 | $8,069,500 | $6,970,000 |
| Roofing and envelope | $3,912,800 | $3,932,700 | $3,992,600 | $4,072,500 | $4,232,200 | $3,690,000 |
| Doors and windows | $2,151,600 | $2,173,800 | $2,195,900 | $2,218,100 | $2,306,800 | $2,050,000 |
| Finishes | $4,709,100 | $4,831,100 | $4,782,300 | $4,977,500 | $5,123,900 | $4,510,000 |
| Specialties and equipment | $851,800 | $860,600 | $887,200 | $896,100 | $940,500 | $820,000 |
| Conveying | $878,400 | $887,200 | $878,400 | $887,200 | $913,900 | $820,000 |
| Plumbing and fire protection | $3,912,800 | $3,932,700 | $3,972,700 | $4,112,400 | $4,272,100 | $3,690,000 |
| HVAC | $3,027,700 | $3,043,300 | $3,105,400 | $3,167,500 | $3,291,700 | $2,870,000 |
| Electrical and low voltage | $3,478,000 | $3,495,800 | $3,513,500 | $3,584,500 | $3,726,400 | $3,280,000 |
| General conditions, fee, insurance and bond | ||||||
| General conditions | $2,556,000$106,500 a month, 24 months | $2,635,200$109,800 a month, 24 months | $2,367,200$107,600 a month, 22 months | $2,767,200$115,300 a month, 24 months | $3,022,500$120,900 a month, 25 months | $2,460,000 |
| Contractor fee | $1,422,2153.50% | $1,746,5504.25% | $1,553,3284.00% | $1,914,2194.50% | $2,215,3105.00% | $1,640,000 |
| Insurance | $399,5410.95% | $449,8391.05% | $403,8651.00% | $488,9771.10% | $558,2581.20% | $492,000 |
| Payment and performance bond | $275,9670.65% | $311,7000.72% | $285,5330.70% | $337,0600.75% | $376,6380.80% | $328,000 |
| Face totalAs submitted | $42,732,422 | $43,603,390 | $41,075,926 | $45,278,456 | $47,456,406 | $41,000,000 |
| Leveling adjustments | ||||||
| Plugs for excluded scopeMedian of the other bids | None | None | +$2,228,700 | None | None | |
| Owner allowancesCarried at the owner's amounts | -$35,000 | +$50,000 | +$220,000 | +$75,000 | -$125,000 | |
| Scope checklistLines marked away from the owner's intent | +$260,000 | +$95,000 | +$300,0001 line not priced | -$412,000 | -$399,000 | |
| Unit pricesRates at the owner's quantities | +$1,135,500 | +$997,000 | +$946,000 | +$1,054,000 | +$1,067,000 | |
| Owner alternatesNone selected | None | None | None | None | None | |
| Leveled total | $44,092,922 | $44,745,390 | $44,770,626Before exclusions priced | $45,995,456 | $47,999,406 | $41,000,000 |
| Per unit | $220,465 | $223,727 | $223,853 | $229,977 | $239,997 | $205,000 |
| Per gross SF | $138.86 | $140.91 | $140.99 | $144.85 | $151.16 | $129.12 |
| Against budget | Over budget $3.1M | Over budget $3.7M | Over budget $3.8M | Over budget $5.0M | Over budget $7.0M | |
| ExclusionsScope left out, priced in leveling | 2 exclusions3 qualifications | 1 exclusion1 qualification | 4 exclusions5 qualifications | None2 qualifications | None2 qualifications | |
| Addenda acknowledged | 1, 2 | 1, 2 | 1, 2 | 1, 2 | 1Missing 2 | |
| Months to complete | 24 months | 24 months | 22 months | 24 months | 25 months | 24 months |
Leveling method
Leveling method, in order. 1. Allowances: each bid's figure for every owner allowance scope is replaced with the owner's amount, and any allowance a GC carried for a unit-price item is removed. 2. Excluded divisions: a division a GC excluded is filled with the median of the other bids' allowance-normalized lines for that division (the average of the two middle values when there are four). 3. Checklist: each line a GC marked differently from the owner's intent is added or deducted at the stated reference amount; a line with no reference is listed and the total is shown as before exclusions priced. 4. Unit prices: each bid's rates extended at the owner's quantities. Adjustments are at cost: the bid's own fee, insurance and bond rates are not applied to them. 5. Owner alternates: each one selected is added to or deducted from every bid at that bid's price; a bid that left it unpriced takes the median of the others. Ranking is by the leveled total.
Owner alternates count only when selected, and then in every bid. Other alternates a bidder offered are listed, never totaled.
Budget column: the hard cost budget split by the program build-up's division shares, a sample split that sums to the budget.
Sample activity and dates. Bid is the leveled total.
- SubmittedOct 9
- SubmittedOct 8
- SubmittedOct 9
- SubmittedOct 7
- SubmittedOct 9
- DeclinedSep 24
| General contractor | Status | Last activity | Questions asked | Bid |
|---|---|---|---|---|
| Submitted | Oct 9 | 2 | $44,092,922 | |
| Submitted | Oct 8 | 1 | $44,745,390 | |
| Submitted | Oct 9 | 3 | $44,770,626 | |
| Submitted | Oct 7 | 1 | $45,995,456 | |
| Submitted | Oct 9 | 0 | $47,999,406 | |
| Declined | Sep 24 | 0 | None |
Email drafts
Drafts only. Apolis sends nothing; you send from your own mail.
What the GCs price
Issued Friday, September 18, 2026. One package and one return form for 6 general contractors.
Stage and estimate class
Feasibility, going into schematic design
Class 5 to Class 4, about -50% / +100% (Class 5) to -30% / +50% (Class 4). A range per unit and per gross SF, with a conceptual budget by division. Not a lump sum.
Why the stage matters, and every design stage
A GC asked for a hard number off a massing either declines or pads it. Stating the stage and the estimate class says which number is wanted and how much accuracy is expected. The package is reissued at schematic design (Class 4) with drawings, the survey and the geotech report, and priced again on the same return form.
This package prices 4 over 1 (four wood-frame stories over one concrete podium story), the building the deal page and the spec book describe. The architect's test fit confirms it, and the package is reissued if it changes.
Feasibility
This package
- AACE class
- Class 5 to Class 4
- Defined
- 0 to 15% of the project defined
- Accuracy
- about -50% / +100% (Class 5) to -30% / +50% (Class 4)
- Owner provides
- Unit count and mix, gross and net SF, stories, construction type, parking count and type, location, target start, finish level
- Number returned
- A range per unit and per gross SF, with a conceptual budget by division
Schematic design
- AACE class
- Class 4
- Defined
- 1 to 15% of the project defined
- Accuracy
- about -30% / +50%
- Owner provides
- Site plan, floor plans, sections, elevations, structural and MEP narratives, outline spec, geotech, survey
- Number returned
- A conceptual estimate by division, allowances named, a value engineering list
Design development
- AACE class
- Class 3
- Defined
- 10 to 40% of the project defined
- Accuracy
- about -20% / +30%
- Owner provides
- Dimensioned plans, wall types, door and window schedules, MEP layouts, outline specs
- Number returned
- A detailed estimate by division; often the GMP basis in negotiated work
Construction documents
- AACE class
- Class 2 to Class 1
- Defined
- Bid documents, new buildings often 70 to 80% complete at bid
- Accuracy
- Priced to the documents
- Owner provides
- Permit set, project manual, bid form, addenda
- Number returned
- A lump sum or GMP with subcontractor bids three deep
| Stage | AACE class | Defined | Accuracy | Owner provides | Number returned |
|---|---|---|---|---|---|
| FeasibilityThis package | Class 5 to Class 4 | 0 to 15% of the project defined | about -50% / +100% (Class 5) to -30% / +50% (Class 4) | Unit count and mix, gross and net SF, stories, construction type, parking count and type, location, target start, finish level | A range per unit and per gross SF, with a conceptual budget by division |
| Schematic design | Class 4 | 1 to 15% of the project defined | about -30% / +50% | Site plan, floor plans, sections, elevations, structural and MEP narratives, outline spec, geotech, survey | A conceptual estimate by division, allowances named, a value engineering list |
| Design development | Class 3 | 10 to 40% of the project defined | about -20% / +30% | Dimensioned plans, wall types, door and window schedules, MEP layouts, outline specs | A detailed estimate by division; often the GMP basis in negotiated work |
| Construction documents | Class 2 to Class 1 | Bid documents, new buildings often 70 to 80% complete at bid | Priced to the documents | Permit set, project manual, bid form, addenda | A lump sum or GMP with subcontractor bids three deep |
Estimate classes per AACE 18R-97; accuracy bands vary by source.
Building
- Project
- Illustrative: 200-unit multifamily development
- Location
- West End, St. Louis Park, Minnesota (sample site; no street address is given for an illustrative deal)
- Construction type priced
- 4 over 1: Four wood-frame stories over one concrete podium story
- Stories
- 5 (4 wood over 1 podium)
- Units
- 200
- Net rentable
- 179,000 SF at 82.0% efficiency
- Gross residential
- 218,293 SF
- Total gross building
- 317,543 SF, floor plate 54,573 SF
- Parking
- 230 stalls, podium parking, 86,250 SF; 46 EV ready
- Construction
- 24 months, month 1 (Feb 2027) to month 24 (Jan 2029)
- Number held for
- 60 days
Studio
- Units
- 30
- Bed / bath
- 0 / 1
- SF each
- 535
- Total SF
- 16,050
1BR
- Units
- 80
- Bed / bath
- 1 / 1
- SF each
- 715
- Total SF
- 57,200
2BR
- Units
- 75
- Bed / bath
- 2 / 2
- SF each
- 1,150
- Total SF
- 86,250
3BR
- Units
- 15
- Bed / bath
- 3 / 2
- SF each
- 1,300
- Total SF
- 19,500
Total
- Units
- 200
- Bed / bath
- SF each
- Total SF
- 179,000
| Type | Units | Bed / bath | SF each | Total SF |
|---|---|---|---|---|
| Studio | 30 | 0 / 1 | 535 | 16,050 |
| 1BR | 80 | 1 / 1 | 715 | 57,200 |
| 2BR | 75 | 2 / 2 | 1,150 | 86,250 |
| 3BR | 15 | 3 / 2 | 1,300 | 19,500 |
| Total | 200 | 179,000 |
Area program (5 areas)
From the building program, 4 over 1. Areas only; the GC prices them.
Net rentable (units)
- Construction
- Wood-frame residential
- SF
- 179,000
- Share of gross
- 56.4%
Corridors, stairs and common
- Construction
- Wood-frame residential
- SF
- 39,293
- Share of gross
- 12.4%
Amenity
- Construction
- Amenity
- SF
- 8,000
- Share of gross
- 2.5%
Leasing and back of house
- Construction
- Podium concrete
- SF
- 5,000
- Share of gross
- 1.6%
Podium parking
- Construction
- Podium concrete
- SF
- 86,250
- Share of gross
- 27.2%
Total gross building
- Construction
- SF
- 317,543
- Share of gross
- 100.0%
| Area | Construction | SF | Share of gross |
|---|---|---|---|
| Net rentable (units) | Wood-frame residential | 179,000 | 56.4% |
| Corridors, stairs and common | Wood-frame residential | 39,293 | 12.4% |
| Amenity | Amenity | 8,000 | 2.5% |
| Leasing and back of house | Podium concrete | 5,000 | 1.6% |
| Podium parking | Podium concrete | 86,250 | 27.2% |
| Total gross building | 317,543 | 100.0% |
Parking and back of house need 91,250 SF against a podium footprint of 54,573 SF under the tower; the architect closes the 36,677 SF difference with a below grade level or a podium larger than the wood floors above it.
Spec book highlights
Unit interiors
- Countertops
- Quartz, 3 cm, eased edge, kitchens and baths
- Cabinets
- Flat panel, soft close, two tone scheme by floor
- Flooring
- Luxury vinyl plank throughout; porcelain tile at baths
- Appliances
- Stainless package, electric range, French door refrigerator, dishwasher, microwave
- Laundry
- Full size stacked washer and dryer in every unit
- Ceilings
- 9 feet typical; 10 feet on the top floor
- Windows
- Double pane vinyl, low E, solar shades in living rooms
- Smart features
- Keyless entry, smart thermostat, leak sensors at wet walls
Amenities
- Fitness
- 2,100 square feet, strength and cardio, on demand studio
- Rooftop terrace
- Grills, firepit lounge, downtown skyline orientation
- Coworking
- Eight seats, two call rooms, conference room by reservation
- Resident lounge
- Chef's kitchen, private dining, game wall
- Package
- Locker room with cold storage for grocery delivery
- Pets
- Dog run on the podium courtyard and a wash station
- Bikes
- Secured storage for 120 bikes with a repair stand
Building and systems
- Construction
- Four wood-framed stories over one concrete podium story with structured parking (4 over 1)
- Parking
- 230 stalls, podium parking; 46 EV ready
- Elevators
- Two traction cabs serving all floors
- Heating and cooling
- Individual electric heat pumps, unit by unit control
- Metering
- Electric metered to each unit; water submetered and reimbursed
- Connectivity
- Fiber to every unit, building wide managed wifi in amenity areas
- Roof
- TPO membrane, 20 year warranty, solar ready conduit runs
Site and code
Stated only where a published source confirms it; everything else is marked to confirm.
Site and zoning sheet
Published source Owner stated (sample) To confirm
Location
- Value
- West End, St. Louis Park, Minnesota
- Status
- Owner stated (sample)
- Source or who confirms
- Illustrative deal; no street address is given
Parcel ID
- Value
- [PARCEL ID]
- Status
- To confirm
- Source or who confirms
- From the county parcel record and the title commitment
Site area, gross
- Value
- 2.5 acres
- Status
- Owner stated (sample)
- Source or who confirms
- Sample site area, the same figure the city fee tracker uses
Site area, net buildable
- Value
- [NET BUILDABLE ACRES]
- Status
- To confirm
- Source or who confirms
- From the ALTA survey, after easements and setbacks; a test fit uses net, not gross
Zoning district
- Value
- [ZONING DISTRICT]
- Status
- To confirm
- Source or who confirms
- From the St. Louis Park zoning map
Maximum height
- Value
- [MAX HEIGHT]
- Status
- To confirm
- Source or who confirms
- Feet and stories, from the district standards
Density and FAR
- Value
- [DENSITY / FAR]
- Status
- To confirm
- Source or who confirms
- From the district standards
Lot coverage
- Value
- [MAX COVERAGE]
- Status
- To confirm
- Source or who confirms
- From the district standards
Setbacks
- Value
- [FRONT / SIDE / REAR]
- Status
- To confirm
- Source or who confirms
- Setbacks and parking usually limit capacity first
Overlays
- Value
- [OVERLAYS]
- Status
- To confirm
- Source or who confirms
- Shoreland, floodplain, or a planned unit development, if any
Parking minimum
- Value
- [CITY MINIMUM]
- Status
- To confirm
- Source or who confirms
- From the St. Louis Park code; the program's stall count is the owner's market decision either way
Parking in the program
- Value
- 230 stalls
- Status
- Owner stated (sample)
- Source or who confirms
- From the building program
Inclusionary housing
- Value
- Policy applies (200 units; the policy covers new multifamily of 10 or more)
- Status
- Published source
- Source or who confirms
- St. Louis Park inclusionary housing policy
Inclusionary share and AMI tiers
- Value
- [SHARE / AMI TIERS]
- Status
- To confirm
- Source or who confirms
- Not confirmed; take the current percentages and tiers from the city before stating them
Regional SAC
- Value
- $2,485 per SAC unit in 2026; Met Council sets the determination
- Status
- Published source
- Source or who confirms
- Met Council 2026 rates. An owner cost, never in the GC's price
Utility availability
- Value
- [WILL-SERVE STATUS]
- Status
- To confirm
- Source or who confirms
- Sewer, water, electric and gas will-serve letters; see the documents checklist
| Item | Value | Status | Source or who confirms |
|---|---|---|---|
| Location | West End, St. Louis Park, Minnesota | Owner stated (sample) | Illustrative deal; no street address is given |
| Parcel ID | [PARCEL ID] | To confirm | From the county parcel record and the title commitment |
| Site area, gross | 2.5 acres | Owner stated (sample) | Sample site area, the same figure the city fee tracker uses |
| Site area, net buildable | [NET BUILDABLE ACRES] | To confirm | From the ALTA survey, after easements and setbacks; a test fit uses net, not gross |
| Zoning district | [ZONING DISTRICT] | To confirm | From the St. Louis Park zoning map |
| Maximum height | [MAX HEIGHT] | To confirm | Feet and stories, from the district standards |
| Density and FAR | [DENSITY / FAR] | To confirm | From the district standards |
| Lot coverage | [MAX COVERAGE] | To confirm | From the district standards |
| Setbacks | [FRONT / SIDE / REAR] | To confirm | Setbacks and parking usually limit capacity first |
| Overlays | [OVERLAYS] | To confirm | Shoreland, floodplain, or a planned unit development, if any |
| Parking minimum | [CITY MINIMUM] | To confirm | From the St. Louis Park code; the program's stall count is the owner's market decision either way |
| Parking in the program | 230 stalls | Owner stated (sample) | From the building program |
| Inclusionary housing | Policy applies (200 units; the policy covers new multifamily of 10 or more) | Published source | St. Louis Park inclusionary housing policy |
| Inclusionary share and AMI tiers | [SHARE / AMI TIERS] | To confirm | Not confirmed; take the current percentages and tiers from the city before stating them |
| Regional SAC | $2,485 per SAC unit in 2026; Met Council sets the determination | Published source | Met Council 2026 rates. An owner cost, never in the GC's price |
| Utility availability | [WILL-SERVE STATUS] | To confirm | Sewer, water, electric and gas will-serve letters; see the documents checklist |
Owner-furnished documents
- Received
- 2
- Pending
- 2
- Not started
- 3
Sample statuses; no document exists for this illustrative deal.
Code basis: architect to confirm (7 lines)
The owner's stated assumptions, so every GC prices the same basis. Nothing here is a code determination; the architect confirms or changes each line, and the package is reissued if any line changes.
Building code edition
- Assumed for pricing
- 2020 Minnesota State Building Code (2018 IBC), effective March 31, 2020
- Status
- Published source
- Note
- Revisor 1305.0011
2026 code adoption
- Assumed for pricing
- 2026 MSBC (2024 I-codes): effective date to confirm
- Status
- Architect to confirm
- Note
- DLI projected Q3 2026; the Chapter 1305 docket still shows the date as TBD. The architect confirms which edition the permit falls under
Construction type
- Assumed for pricing
- 4 over 1: four wood-frame stories over one concrete podium story. IBC construction type per story to confirm
- Status
- Architect to confirm
- Note
- Architect to confirm the construction type of each story and the podium separation
Sprinkler standard
- Assumed for pricing
- NFPA 13R may serve the 4 wood stories above the podium if the building is 60 feet or less above grade plane; NFPA 13 in the garage podium. A 13R building loses the NFPA 13 trade-offs.
- Status
- Architect to confirm
- Note
- 2018 IBC 903.3.1.2: NFPA 13R to 4 stories and 60 feet above grade plane. Building height is not yet drawn
Energy code
- Assumed for pricing
- Commercial energy code, ASHRAE 90.1-2019 with Minnesota amendments, effective January 5, 2024 (5 stories, above the 3-story residential line)
- Status
- Published source
- Note
- DLI commercial energy code fact sheet. Envelope and ventilation compliance path: architect and MEP engineer to choose
Accessibility
- Assumed for pricing
- Minnesota Rules chapter 1341. Type A unit count: [TYPE A COUNT]
- Status
- Architect to confirm
- Note
- Architect to confirm the Type A count; it moves unit plans and cost
Frost protection
- Assumed for pricing
- Footing depth to confirm
- Status
- Architect to confirm
- Note
- Minnesota Rules 1303.1600; the figure the research note found is from a secondary source, and a DLI group has proposed re-zoning. Structural engineer to confirm
| Topic | Assumed for pricing | Status | Note |
|---|---|---|---|
| Building code edition | 2020 Minnesota State Building Code (2018 IBC), effective March 31, 2020 | Published source | Revisor 1305.0011 |
| 2026 code adoption | 2026 MSBC (2024 I-codes): effective date to confirm | Architect to confirm | DLI projected Q3 2026; the Chapter 1305 docket still shows the date as TBD. The architect confirms which edition the permit falls under |
| Construction type | 4 over 1: four wood-frame stories over one concrete podium story. IBC construction type per story to confirm | Architect to confirm | Architect to confirm the construction type of each story and the podium separation |
| Sprinkler standard | NFPA 13R may serve the 4 wood stories above the podium if the building is 60 feet or less above grade plane; NFPA 13 in the garage podium. A 13R building loses the NFPA 13 trade-offs. | Architect to confirm | 2018 IBC 903.3.1.2: NFPA 13R to 4 stories and 60 feet above grade plane. Building height is not yet drawn |
| Energy code | Commercial energy code, ASHRAE 90.1-2019 with Minnesota amendments, effective January 5, 2024 (5 stories, above the 3-story residential line) | Published source | DLI commercial energy code fact sheet. Envelope and ventilation compliance path: architect and MEP engineer to choose |
| Accessibility | Minnesota Rules chapter 1341. Type A unit count: [TYPE A COUNT] | Architect to confirm | Architect to confirm the Type A count; it moves unit plans and cost |
| Frost protection | Footing depth to confirm | Architect to confirm | Minnesota Rules 1303.1600; the figure the research note found is from a secondary source, and a DLI group has proposed re-zoning. Structural engineer to confirm |
If the architect draws 5 over 1: NFPA 13 throughout: 5 wood stories exceed the 4-story NFPA 13R limit. If the building becomes a Texas wrap: NFPA 13 throughout: 5 wood stories exceed the 4-story NFPA 13R limit.
Owner-furnished documents, one by one (7)
AIA B101 puts the survey and the geotechnical report on the owner, and the architect may rely on them. Their absence is what drives allowances and fee contingencies, so the package says plainly what exists.
ALTA and topographic survey, tied to a benchmark
- Status
- Pending
- What it drives
- Net buildable area, setbacks, the test fit and site utilities
Geotechnical report with borings and a foundation recommendation
- Status
- Not started
- What it drives
- Foundations and the soils unit price quantities; until it arrives, soils are priced only by unit price
Phase I environmental site assessment
- Status
- Received
- What it drives
- Hazardous materials: by owner, and no basis to price until a Phase II is needed or ruled out
Title commitment
- Status
- Received
- What it drives
- Easements that move the building, and the parcel ID
Utility will-serve letters (sewer, water, electric, gas)
- Status
- Pending
- What it drives
- Service sizes, utility company charges, and where site utilities connect
Traffic study, if the city requires one
- Status
- Not started
- What it drives
- Access points and any off-site work
City pre-application meeting notes
- Status
- Not started
- What it drives
- Zoning parameters, parking and the inclusionary requirement
| Document | Status | What it drives |
|---|---|---|
| ALTA and topographic survey, tied to a benchmark | Pending | Net buildable area, setbacks, the test fit and site utilities |
| Geotechnical report with borings and a foundation recommendation | Not started | Foundations and the soils unit price quantities; until it arrives, soils are priced only by unit price |
| Phase I environmental site assessment | Received | Hazardous materials: by owner, and no basis to price until a Phase II is needed or ruled out |
| Title commitment | Received | Easements that move the building, and the parcel ID |
| Utility will-serve letters (sewer, water, electric, gas) | Pending | Service sizes, utility company charges, and where site utilities connect |
| Traffic study, if the city requires one | Not started | Access points and any off-site work |
| City pre-application meeting notes | Not started | Zoning parameters, parking and the inclusionary requirement |
Sources (7)
- Inclusionary housing: St. Louis Park inclusionary housing policy
- Regional SAC: Met Council 2026 rates. An owner cost, never in the GC's price
- Building code edition: Revisor 1305
- 2026 code adoption: DLI projected Q3 2026; the Chapter 1305 docket still shows the date as TBD
- Sprinkler standard: 2018 IBC 903
- Energy code: DLI commercial energy code fact sheet
- Frost protection: Minnesota Rules 1303
Owner schedules
The owner sets allowances, unit price quantities, alternates and the checklist, so every bid shares one basis.
- Owner allowances
- $3,035,000
- 5 lines, carried by every bidder
- Unit price lines
- 4
- a rate for each, at owner quantities
- Checklist lines
- 26
- each marked; a blank reads as excluded
Owner allowances (5)
Every bidder carries exactly these amounts, inside its total, in the division shown. If the work runs over an allowance the owner pays the difference; under, the owner keeps it. A GC that wants a different amount says so as a qualification, not by changing the number.
Landscape and irrigation
- Division
- Sitework
- Why an allowance
- Landscape plan not drawn
- Amount
- $235,000
Signage and wayfinding
- Division
- Specialties and equipment
- Why an allowance
- Brand package not chosen
- Amount
- $75,000
Unit flooring and tile
- Division
- Finishes
- Why an allowance
- Finish level chosen, product not selected
- Amount
- $1,700,000
Unit appliance package
- Division
- Specialties and equipment
- Why an allowance
- Package not selected
- Amount
- $600,000
Low voltage and access control
- Division
- Electrical and low voltage
- Why an allowance
- Access control vendor not chosen
- Amount
- $425,000
Total, carried by every bidder
- Division
- Why an allowance
- Amount
- $3,035,000
| Allowance | Division | Why an allowance | Amount |
|---|---|---|---|
| Landscape and irrigation | Sitework | Landscape plan not drawn | $235,000 |
| Signage and wayfinding | Specialties and equipment | Brand package not chosen | $75,000 |
| Unit flooring and tile | Finishes | Finish level chosen, product not selected | $1,700,000 |
| Unit appliance package | Specialties and equipment | Package not selected | $600,000 |
| Low voltage and access control | Electrical and low voltage | Access control vendor not chosen | $425,000 |
| Total, carried by every bidder | $3,035,000 |
Unit prices (4)
Every bidder quotes a rate for each line. The rates are not in the base bid. To compare bids, leveling extends each rate at the owner's quantity; the quantities are estimates, stated, and are replaced once the geotechnical report is received. A rate more than 25% from the median of the bids' rates for that line is flagged: an unbalanced unit price costs the owner when quantities move.
Unsuitable soils: excavate, haul off and replace with engineered fill
- Unit
- CY
- Owner quantity
- 3,000
- Quantity basis
- Sample quantity until the geotechnical report is received
Rock excavation
- Unit
- CY
- Owner quantity
- 200
- Quantity basis
- Sample quantity until the geotechnical report is received
Dewatering
- Unit
- day
- Owner quantity
- 30
- Quantity basis
- Sample quantity until the geotechnical report is received
Winter conditions: temporary heat, enclosure, frost protection, snow removal
- Unit
- month
- Owner quantity
- 10
- Quantity basis
- Construction months falling November through March, Feb 2027 start to Jan 2029 completion, from the deal schedule
| Item | Unit | Owner quantity | Quantity basis |
|---|---|---|---|
| Unsuitable soils: excavate, haul off and replace with engineered fill | CY | 3,000 | Sample quantity until the geotechnical report is received |
| Rock excavation | CY | 200 | Sample quantity until the geotechnical report is received |
| Dewatering | day | 30 | Sample quantity until the geotechnical report is received |
| Winter conditions: temporary heat, enclosure, frost protection, snow removal | month | 10 | Construction months falling November through March, Feb 2027 start to Jan 2029 completion, from the deal schedule |
Owner alternates (2)
Each bidder prices every owner alternate as an add or deduct. None is in a total until it is selected on the Leveling tab. Sample prices.
Alt 1: Fiber cement in lieu of metal panel above the podium
Deduct
- Builders Co
- -$290,000
- Lakeshore Construction
- -$420,000
- Prairie Contractors
- -$335,000
- Granite Ridge Builders
- -$310,000
- Twin Rivers General
- -$300,000
Alt 2: Rooftop solar array
Add
- Builders Co
- +$610,000
- Lakeshore Construction
- +$655,000
- Prairie Contractors
- +$590,000
- Granite Ridge Builders
- +$640,000
- Twin Rivers General
- Not priced
| Alternate | Builders Co | Lakeshore Construction | Prairie Contractors | Granite Ridge Builders | Twin Rivers General |
|---|---|---|---|---|---|
| Alt 1: Fiber cement in lieu of metal panel above the podiumDeduct | -$290,000 | -$420,000 | -$335,000 | -$310,000 | -$300,000 |
| Alt 2: Rooftop solar arrayAdd | +$610,000 | +$655,000 | +$590,000 | +$640,000 | Not priced |
Inclusions and exclusions checklist (26)
Every bidder marks every line included, excluded or by owner. A blank is read as excluded. Leveling then adjusts line by line: a base-bid line a GC excluded is added at the stated reference amount, and an owner or unit-price line a GC included is deducted at it. A line with no reference yet is listed, not priced.
1. SAC (Met Council sewer availability charge)
- Owner's intent
- By owner
- Reference amount
- $397,600
- Basis
- City fee tracker: 2026 Met Council rate times a sample determination of 160 SAC units
2. City WAC and connection charges
- Owner's intent
- By owner
- Reference amount
- $128,000
- Basis
- City fee tracker: St. Louis Park WAC, published schedule, times 160 SAC units
3. Park dedication
- Owner's intent
- By owner
- Reference amount
- $300,000
- Basis
- City fee tracker: St. Louis Park, published schedule, per unit times 200 units
4. Building permit and plan review fees
- Owner's intent
- By owner
- Reference amount
- $235,000
- Basis
- City fee tracker: St. Louis Park permit and plan review, sample rows; confirm the GC's carried amount
5. Utility company charges (electric and gas service)
- Owner's intent
- By owner
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
6. Testing and special inspections
- Owner's intent
- By owner
- Reference amount
- $222,000
- Basis
- Sample: 0.50% of the program build-up of $44,362,485, deducted where a GC carries it; confirm the GC's carried amount
7. Builder's risk insurance
- Owner's intent
- By owner
- Reference amount
- $177,000
- Basis
- Sample: 0.40% of the program build-up of $44,362,485, deducted where a GC carries it; confirm the GC's carried amount
8. Hazardous materials abatement
- Owner's intent
- By owner
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
9. Amenity furniture and owner FF&E
- Owner's intent
- By owner
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
10. Contractor general liability insurance
- Owner's intent
- In the base bid
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
11. Payment and performance bond
- Owner's intent
- In the base bid
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
12. Winter conditions
- Owner's intent
- By unit price only
- Reference amount
- No basis yet
- Basis
- Priced by the unit price schedule
13. Unsuitable soils correction
- Owner's intent
- By unit price only
- Reference amount
- No basis yet
- Basis
- Priced by the unit price schedule
14. Rock excavation
- Owner's intent
- By unit price only
- Reference amount
- No basis yet
- Basis
- Priced by the unit price schedule
15. Dewatering
- Owner's intent
- By unit price only
- Reference amount
- No basis yet
- Basis
- Priced by the unit price schedule
16. Temporary power, water and heat for the work (other than winter conditions)
- Owner's intent
- In the base bid
- Reference amount
- $180,000
- Basis
- Sample: temporary utilities over the 24-month construction window, added where excluded
17. Erosion control and stormwater permit compliance
- Owner's intent
- In the base bid
- Reference amount
- $95,000
- Basis
- Sample: erosion control and inspections, added where excluded
18. Site utilities from 5 feet outside the building to the mains
- Owner's intent
- In the base bid
- Reference amount
- $310,000
- Basis
- Sample: site utilities to the mains, added where excluded
19. Construction layout and staking
- Owner's intent
- In the base bid
- Reference amount
- $60,000
- Basis
- Sample: layout from the owner's survey control, added where excluded
20. Delegated design (trusses, sprinklers, fire alarm)
- Owner's intent
- In the base bid
- Reference amount
- $140,000
- Basis
- Sample: delegated engineering, added where excluded
21. Low voltage, access control and fiber backbone
- Owner's intent
- In the base bid
- Reference amount
- $425,000
- Basis
- The owner allowance amount, added where excluded
22. Unit appliances
- Owner's intent
- In the base bid
- Reference amount
- $600,000
- Basis
- The owner allowance amount, added where excluded
23. Signage and wayfinding
- Owner's intent
- In the base bid
- Reference amount
- $75,000
- Basis
- The owner allowance amount, added where excluded
24. Landscape and irrigation
- Owner's intent
- In the base bid
- Reference amount
- $235,000
- Basis
- The owner allowance amount, added where excluded
25. Window treatments
- Owner's intent
- In the base bid
- Reference amount
- No basis yet
- Basis
- Listed, not priced, if a bid departs from the intent
26. Final cleaning
- Owner's intent
- In the base bid
- Reference amount
- $120,000
- Basis
- Sample: final clean of units and common areas, added where excluded
| Line | Owner's intent | Reference amount | Basis |
|---|---|---|---|
| 1. SAC (Met Council sewer availability charge) | By owner | $397,600 | City fee tracker: 2026 Met Council rate times a sample determination of 160 SAC units |
| 2. City WAC and connection charges | By owner | $128,000 | City fee tracker: St. Louis Park WAC, published schedule, times 160 SAC units |
| 3. Park dedication | By owner | $300,000 | City fee tracker: St. Louis Park, published schedule, per unit times 200 units |
| 4. Building permit and plan review fees | By owner | $235,000 | City fee tracker: St. Louis Park permit and plan review, sample rows; confirm the GC's carried amount |
| 5. Utility company charges (electric and gas service) | By owner | No basis yet | Listed, not priced, if a bid departs from the intent |
| 6. Testing and special inspections | By owner | $222,000 | Sample: 0.50% of the program build-up of $44,362,485, deducted where a GC carries it; confirm the GC's carried amount |
| 7. Builder's risk insurance | By owner | $177,000 | Sample: 0.40% of the program build-up of $44,362,485, deducted where a GC carries it; confirm the GC's carried amount |
| 8. Hazardous materials abatement | By owner | No basis yet | Listed, not priced, if a bid departs from the intent |
| 9. Amenity furniture and owner FF&E | By owner | No basis yet | Listed, not priced, if a bid departs from the intent |
| 10. Contractor general liability insurance | In the base bid | No basis yet | Listed, not priced, if a bid departs from the intent |
| 11. Payment and performance bond | In the base bid | No basis yet | Listed, not priced, if a bid departs from the intent |
| 12. Winter conditions | By unit price only | No basis yet | Priced by the unit price schedule |
| 13. Unsuitable soils correction | By unit price only | No basis yet | Priced by the unit price schedule |
| 14. Rock excavation | By unit price only | No basis yet | Priced by the unit price schedule |
| 15. Dewatering | By unit price only | No basis yet | Priced by the unit price schedule |
| 16. Temporary power, water and heat for the work (other than winter conditions) | In the base bid | $180,000 | Sample: temporary utilities over the 24-month construction window, added where excluded |
| 17. Erosion control and stormwater permit compliance | In the base bid | $95,000 | Sample: erosion control and inspections, added where excluded |
| 18. Site utilities from 5 feet outside the building to the mains | In the base bid | $310,000 | Sample: site utilities to the mains, added where excluded |
| 19. Construction layout and staking | In the base bid | $60,000 | Sample: layout from the owner's survey control, added where excluded |
| 20. Delegated design (trusses, sprinklers, fire alarm) | In the base bid | $140,000 | Sample: delegated engineering, added where excluded |
| 21. Low voltage, access control and fiber backbone | In the base bid | $425,000 | The owner allowance amount, added where excluded |
| 22. Unit appliances | In the base bid | $600,000 | The owner allowance amount, added where excluded |
| 23. Signage and wayfinding | In the base bid | $75,000 | The owner allowance amount, added where excluded |
| 24. Landscape and irrigation | In the base bid | $235,000 | The owner allowance amount, added where excluded |
| 25. Window treatments | In the base bid | No basis yet | Listed, not priced, if a bid departs from the intent |
| 26. Final cleaning | In the base bid | $120,000 | Sample: final clean of units and common areas, added where excluded |
What is requested (9 items)
- A range per unit and per gross SF, with a conceptual budget by division (Class 5 to Class 4). Not a lump sum.
- The total broken down on the return form's 15 lines, which must sum to it: general conditions as a monthly rate times months, fee as a percentage, insurance and bond as their own rates.
- The owner's 5 allowances carried at exactly the stated amounts.
- A rate for each of the 4 unit price lines.
- Every one of the 26 checklist lines marked included, excluded or by owner; a blank is read as excluded.
- Each of the 2 owner alternates priced as an add or deduct; any other alternate listed separately.
- Qualifications, one per line.
- A proposed construction duration against the 24 month schedule, and the number held for 60 days.
- Addenda acknowledged, by number.
Who receives it (9 sample firms)
Sample firms, no outreach has occurred.
Sample Builders Co
General contractor, wood frame over podium, the project team's named GC
precon@sample-builders.example.com
Sample Lakeshore Construction
General contractor, mid-rise multifamily
estimating@sample-lakeshore.example.com
Sample Prairie Contractors
General contractor, podium and wrap multifamily
bids@sample-prairie.example.com
Sample Granite Ridge Builders
General contractor, concrete and wood frame
precon@sample-graniteridge.example.com
Sample Twin Rivers General
General contractor, multifamily and mixed use
estimating@sample-twinrivers.example.com
Sample Northstar Builders
General contractor, wood frame multifamily
precon@sample-northstar.example.com
Sample Architecture Studio
Architect of record, the project team's named architect
studio@sample-architecture.example.com
Sample Northline Architects
Architect, multifamily feasibility and schematic design
proposals@sample-northline.example.com
Sample Commons Design Group
Architect, podium and wrap housing
hello@sample-commons.example.com
What each GC fills in
15 lines summing to the total, then allowances, unit prices, alternates and the checklist.
| Line | Scope | Amount |
|---|---|---|
| General conditionsDiv 01Field supervision, temporary facilities, cleanup; a monthly rate times months | Field supervision, temporary facilities, cleanup; a monthly rate times months | Monthly rate × months |
| SiteworkDiv 31, 32, 33Earthwork, site utilities to the mains, paving, landscape | Earthwork, site utilities to the mains, paving, landscape | |
| ConcreteDiv 03, 04Foundations, podium slab and structure, masonry | Foundations, podium slab and structure, masonry | |
| Framing and carpentryDiv 05, 06Wood framing, trusses, sheathing, misc metals, finish carpentry | Wood framing, trusses, sheathing, misc metals, finish carpentry | |
| Roofing and envelopeDiv 07Roofing, insulation, air barrier, cladding, sealants | Roofing, insulation, air barrier, cladding, sealants | |
| Doors and windowsDiv 08Unit and common doors, hardware, windows, storefront | Unit and common doors, hardware, windows, storefront | |
| FinishesDiv 09Drywall, flooring, tile, paint, ceilings | Drywall, flooring, tile, paint, ceilings | |
| Specialties and equipmentDiv 10, 11, 12Appliances, cabinets and countertops, signage, mailboxes, lockers | Appliances, cabinets and countertops, signage, mailboxes, lockers | |
| ConveyingDiv 14Elevators | Elevators | |
| Plumbing and fire protectionDiv 21, 22Sprinklers to the stated basis, domestic water, waste, fixtures | Sprinklers to the stated basis, domestic water, waste, fixtures | |
| HVACDiv 23Unit heat pumps, ventilation, garage exhaust | Unit heat pumps, ventilation, garage exhaust | |
| Electrical and low voltageDiv 26, 27, 28Power, lighting, fire alarm, access control, fiber | Power, lighting, fire alarm, access control, fiber | |
| Contractor feeNo CSI divisionA percentage of the cost of the work (trades plus general conditions) | A percentage of the cost of the work (trades plus general conditions) | Fee % × cost of the work |
| InsuranceNo CSI divisionContractor general liability, a rate on cost plus fee; builder's risk is by owner | Contractor general liability, a rate on cost plus fee; builder's risk is by owner | Rate × (cost of the work + fee) |
| Payment and performance bondNo CSI divisionA rate on cost plus fee plus insurance | A rate on cost plus fee plus insurance | Rate × (cost + fee + insurance) |
| Total (the lines must sum to it) | ||
| Range: low and high, per gross SF | ||
| Total per unit | ||
| Total per gross SF |
Owner allowances, carried as printed
- Landscape and irrigation$235,000
- Signage and wayfinding$75,000
- Unit flooring and tile$1,700,000
- Unit appliance package$600,000
- Low voltage and access control$425,000
Unit prices, a rate for each
- Unsuitable soilsper CY
- Rock excavationper CY
- Dewateringper day
- Winter conditionsper month
Owner alternates, add or deduct
- Alt 1: Fiber cement in lieu of metal panel above the podium
- Alt 2: Rooftop solar array
- Checklist: each of the 26 lines marked Included, Excluded or By owner. A blank is read as excluded.
- Qualifications: one per line
- Proposed construction duration, months
- Number held for 60 days (or state the date)
- Addenda acknowledged, by number
- Contact for questions
Duration is read against the 24 month schedule. Nothing here is a contract or an invitation to contract; the return form is a pricing request.