Sources · equity funds first
$52.2M
- Investor equity$17.7M34.0%
- Sponsor co-investment$548K1.1%
- Construction loan$33.9M65.0%
- Total sources$52.2M
Uses, by budget section $52.2M, 11 sections
Uses · by budget section
$52.2M
- Hard costs$41.0M78.6%
- Capitalized interest and loan fees$2.3M4.4%
- Developer fee$2.0M3.9%
- Land and acquisition$2.0M3.8%
- City and government$1.6M3.1%
- Design and consultants$1.2M2.3%
- FF&E and pre-opening marketing$625K1.2%
- Contingency and rounding$489K0.9%
- Financing, title and closing$418K0.8%
- Carry and pre-open operating$290K0.6%
- Legal, accounting and equity$212K0.4%
- Total uses$52.2M
Sponsor
Sample Sponsor LLC
- Units delivered6 projects
- 600
- Actual against projected NOI
- 2 of 5 below projection
- GP commitment3.0% of equity, pari passu
- $548K
Top three risks
- Refinance rate. At the 7.15% stress the permanent loan sizes to $39.0M against $47.0M, reducing the month 61 distribution.
- Lease-up deficit. Modelled $1.2M against a $101K reserve. The $1.1M balance is a sponsor commitment, form not stated.
- Construction loan term. Base case requires both extensions (months 42 and 54): maturity month 42, refinance month 61. Extension fees of $169,611 are not in the cash flow.
Terms
- Preferred returnaccrues, compounds annually
- 8%
- Hold and exitsale at a 5.50% exit cap
- 10 years
- Refinance, month 61about $7.7M capital, about $7.0M accrued preferred return
- $14.0M
- Distributionsoperations from year 4, refinance month 61, sale month 120
- $49.9M
- DebtSOFR plus 275 basis points, interest only, 42 months plus two 12-month extensions; permanent assumed at 5.40% fixed
- 65% LTC
- Sponsor fees over the hold Fee tabledevelopment fee $2.0M, asset management fee $1.5M, promote $7.5M
- $11.0M
The property
- Units
- 200
- 4 plans
- Building
- 4 over 1
- 5 stories, 1 podium
- Net rentable SF
- 179,000
- 895 SF average unit
- Gross SF
- 317,543
- the building program, podium and parking included
- Parking
- 230 stalls
- Podium parking, 1.15 per unit
- Site
- 2.5 acres
- West End, St. Louis Park, Minnesota
- Entitlement
- Complete
- Approval recorded, appeal period run
- Construction start
- Feb 2027
- month 1
- First delivery
- Feb 2029
- month 25
- Stabilization
- Jan 2030
- 11 months of lease-up
- Hold
- 10 years
- sale Jan 2037
- Strategy
- Ground-up development
Amenities: Fitness, Rooftop terrace, Coworking, Resident lounge, Package, Pets, Bikes
- Studio3015.0%535 SF$1,625$3.04/SF
- 1BR8040.0%715 SF$1,850$2.59/SF
- 2BR7537.5%1,150 SF$2,550$2.22/SF
- 3BR157.5%1,300 SF$3,250$2.50/SF
| Type | Units | % of total | Average size | Pro forma rent | Rent per SF |
|---|---|---|---|---|---|
| Studio | 30 | 15.0% | 535 SF | $1,625 | $3.04/SF |
| 1BR | 80 | 40.0% | 715 SF | $1,850 | $2.59/SF |
| 2BR | 75 | 37.5% | 1,150 SF | $2,550 | $2.22/SF |
| 3BR | 15 | 7.5% | 1,300 SF | $3,250 | $2.50/SF |
| Total or average | 200 | 100.0% | 895 SF | $2,184 | $2.44/SF |
Total or average200 units · 895 SF · $2,184 · $2.44/SF
Unit mix as a bar the same counts as the table
Unit mix
200 units
- Studio30 units15.0%
- 1BR80 units40.0%
- 2BR75 units37.5%
- 3BR15 units7.5%
Schedule, closing to sale 7 milestones
Closing
Jan 2027
month 0
Construction start
Feb 2027
month 1
Construction complete
Jan 2029
month 24
First delivery
Feb 2029
month 25
Stabilized
Jan 2030
month 36
Refinance
Feb 2032
month 61
Sale
Jan 2037
month 120
The site and what is nearby
Nearby draws within 2 miles, straight-line distance
Grocery
- Cub Foods0.15 mi
- Shanghai Market1.3 mi
- The Kosher Spot1.5 mi
Transit and LRT
- West 21st Street1.7 mi
- Beltline Boulevard1.8 mi
- Bryn Mawr1.8 mi
Parks
- Cedarhurst Park0.43 mi
- Golden Hills Pond0.52 mi
- Blackstone Park0.57 mi
Schools
- Barry Family Campus0.68 mi
- Meadowbrook Elementary School0.68 mi
- Benilde-St. Margaret's0.79 mi
Major employers
- Cyber Optics Corporation0.52 mi
- Laser Design (GKS Services)0.53 mi
- STOROpack Packaging Systems USA0.91 mi
Places: © OpenStreetMap contributors (ODbL), collected 2026-11-08.
The offer
Where the money goes
From what the building can bill to whose pocket it lands in.
Show as a tableHide the table
Gross potential rent$5.7M
Other income$366K
Total potential income$6.1M
Less vacancy$286K
Less concessions$29K
Less credit loss$22K
Effective gross income$5.8M
Less operating expenses$1.6M
Less property tax$408K
Net operating income$3.8M
Less capital reserve$100K
Less debt service$2.4M
Cash to equity$1.3M
Tier 1, preferred return$1.3M
To investors$1.3M
To the sponsorthe preferred return absorbs it$0
How to read this chart
The first stabilized year shows one year of operations; the whole hold adds the refinance and the sale and shows the split between investors and the sponsor. Every stage conserves, so nothing can be left out.
The last two stages are the waterfall at work. This year's whole distribution dies inside tier one: the preferred return accrued on invested capital exceeds the year's cash, so every dollar goes to investors and the sponsor's share is zero. Tiers two through five open only in the bigger years. The whole hold view shows where they do.
Show as a tableHide the table
Operating cashyears 4 to 10$7.3M
Refinance proceedsyear 6$14.0M
Sale proceeds, netyear 10$35.1M
Distributed to equity$56.4M
To the sponsor$7.5M
To investors$49.0M
Capital backto investors$18.3M
Preferred returnto investors$13.2M
Profit shareto investors$17.5M
Promoteto the sponsor$7.5M
How to read this chart
The first stabilized year shows one year of operations; the whole hold adds the refinance and the sale and shows the split between investors and the sponsor. Every stage conserves, so nothing can be left out.
Over the 10-year hold the deal distributes $56.4M: $7.3M of operating cash, $14.0M from the refinance and $35.1M from the sale. The five tiers send $49.0M (87%) to investors as capital back, preferred return and their share of profit, and $7.5M (13%) to the sponsor as promote. The sponsor's co-investment earns alongside investors and sits on the investors' side.
The offer, in one paragraph
This is a 200-unit ground-up development in West End, St. Louis Park, Minnesota, built over 24 months and held for 10 years. It costs $52.2M to build ($260,945 per unit), funded with $33.9M of construction debt (65% of cost) and $18.3M of equity. It fills to stabilized occupancy 11 months after the first units deliver. The month 61 refinance distributes $14.0M: about $7.7M returns capital and about $7.0M pays accrued preferred return. The building sells in month 120 at a 5.50% cap. Investors are projected to receive $49.9M over the hold, 2.73 times their capital, an IRR of 15.16%.
Entitlements are complete: city council approval is recorded and the appeal period expired without challenge. The ten standard diligence questions, including fees, reserves and reporting, are answered under Diligence below.
Location and market
- Subject average rent · pro forma
- $2,184
- $2.44 per SF
- Comp median ask · as of 2026-11-08
- $2,368
- $2.43 per SF
- Comps responding
- 4 of 10
- 28 priced plans, West End
- Running a concession
- 3 of 4
- responding properties
- Studio$1,625$1,599$26 above
- 1BR$1,850$1,849$1 above
- 2BR$2,550$2,578$28 below
- 3BR$3,250None postedNo comp
| Type | Pro forma | Comp median ask | Comp effective | Ours / comp per SF | Against median | Details |
|---|---|---|---|---|---|---|
| Studio | $1,625 | $1,599 | $1,466 | $3.04 / $2.78 | $26 above | |
| 1BR | $1,850 | $1,849 | $1,691 | $2.59 / $2.53 | $1 above | |
| 2BR | $2,550 | $2,578 | $2,388 | $2.22 / $2.34 | $28 below | |
| 3BR | $3,250 | None posted | None posted | $2.50 / None posted | No comp |
Studio against the comps
Pro forma asks $26 above the West End median for a studio, across 5 posted plans.
- Pro forma rent
- $1,625
- Pro forma SF
- 535
- Pro forma per SF
- $3.04
- Comp median ask
- $1,599
- Comp effective median
- $1,466
- Comp range
- $1,299 to $1,630
- Comp median per SF
- $2.78
- Posted plans
- 5
- Properties posting
- 2
1BR against the comps
Pro forma asks $1 above the West End median for a one bedroom, across 7 posted plans.
- Pro forma rent
- $1,850
- Pro forma SF
- 715
- Pro forma per SF
- $2.59
- Comp median ask
- $1,849
- Comp effective median
- $1,691
- Comp range
- $1,799 to $2,005
- Comp median per SF
- $2.53
- Posted plans
- 7
- Properties posting
- 4
2BR against the comps
Pro forma asks $28 below the West End median for a two bedroom, across 16 posted plans.
- Pro forma rent
- $2,550
- Pro forma SF
- 1150
- Pro forma per SF
- $2.22
- Comp median ask
- $2,578
- Comp effective median
- $2,388
- Comp range
- $2,355 to $3,470
- Comp median per SF
- $2.34
- Posted plans
- 16
- Properties posting
- 4
3BR against the comps
No tracked West End property posts a three bedroom ask today. The row waits for a posted comp rather than inventing one.
- Pro forma rent
- $3,250
- Pro forma SF
- 1300
- Pro forma per SF
- $2.50
- Comp median ask
- None posted
- Comp effective median
- None posted
- Comp range
- None posted
- Comp median per SF
- None posted
- Posted plans
- 0
- Properties posting
- 0
Location and the comp set site diagram, distances, every tracked property
Location
The site in its street grid, drawn as a schematic: the parcel, the ring of units over the podium garage, and the transit line it sits on. Sample geography, shown to set the format.
- Site parcel (sample)
- Light rail stop (sample)
- Transit line on Sample Ave N, the horizontal street
- Sample 3rd St, the vertical street beside the parcel
- North is up
- Light rail stop
- 6 minwalk, sample
- Grocery anchor
- 9 minwalk, sample
- University and hospital employment
- 12 mindrive, sample
- Downtown core
- 10 mindrive, sample
- Riverfront park
- 7 minwalk, sample
- Airport
- 21 mindrive, sample
Sample anchors with sample times. On a live deal this card carries the parcel map and true walk and drive isochrones, computed from the address rather than stated.
The comp set
West End, St. Louis Park, and the competing west metro: the comp set the sponsor selected for this sample. Every property below posts its asking rents on its own website; collected 2026-11-08.
Caraway West End
- Plans priced
- 8
- Median ask
- $2,570
- Median $/SF
- $2.57
Concession: None posted
The Shoreham
- Plans priced
- 8
- Median ask
- $1,814
- Median $/SF
- $2.43
Concession: One month free, plus 3 months free garage
Millennium at West End
- Plans priced
- 6
- Median ask
- $2,578
- Median $/SF
- $2.36
Concession: Up to one month free
The Flats at West End
- Plans priced
- 6
- Median ask
- $2,368
- Median $/SF
- $2.34
Concession: 6 weeks free
| Property | Plans priced | Median ask | Median $/SF | Concession |
|---|---|---|---|---|
| Caraway West End | 8 | $2,570 | $2.57 | None posted |
| The Shoreham | 8 | $1,814 | $2.43 | One month free, plus 3 months free garage |
| Millennium at West End | 6 | $2,578 | $2.36 | Up to one month free |
| The Flats at West End | 6 | $2,368 | $2.34 | 6 weeks free |
Year built, unit count and distance to the subject are not yet collected for this set.
Blended rent per square foot, subject on the ladder
Caraway West End
Subject (pro forma)
The Shoreham
Millennium at West End
The Flats at West End
Axis starts at $2.00 per square foot, not zero, so differences of a few cents are visible. Bar lengths compare position on the ladder, not the size of the rent.
On a blended basis the pro forma asks $2.44 per square foot, second of 5 on a ladder of 4 priced properties in the comp set the sponsor selected for this sample.
Comp rungs are the median of each property's posted plans; the subject rung is the unit-weighted average across all 200 pro forma units, a different statistic. A blended figure moves when the unit mix moves, so this ladder is a positioning read, not a comp: the like-for-like read is the card below, joined on bed count. 6 of the 10 tracked properties post no usable pricing and sit off the ladder; their reasons, every posted plan, and the nightly history live on the comps page. The subject rung is rung 2: a pro forma claim on a building that has not been built, not a posted ask.
Pro forma against the market today
Our unit rents against every plan the tracked West End set posts at the same bed count. The gray band is the span of posted asks with its median ticked; the navy mark is our pro forma.
3 of our 4 unit types have at least 3 posted comps behind them; against the medians our rents sit 2BR below, Studio and 1BR above; 3BR has no posted comp and needs a sponsor comp.
Studio
Pro forma $1,625 on 535 SF
Pro forma asks $26 above the West End median for a studio, across 5 posted plans.
Ask median $1,599; effective median $1,466 after posted concessions.
Per square foot: $3.04 pro forma against $2.78 at the comp median, 5 plans across 2 properties.
1BR
Pro forma $1,850 on 715 SF
Pro forma asks $1 above the West End median for a one bedroom, across 7 posted plans.
Ask median $1,849; effective median $1,691 after posted concessions.
Per square foot: $2.59 pro forma against $2.53 at the comp median, 7 plans across 4 properties.
2BR
Pro forma $2,550 on 1,150 SF
Pro forma asks $28 below the West End median for a two bedroom, across 16 posted plans.
Ask median $2,578; effective median $2,388 after posted concessions.
Per square foot: $2.22 pro forma against $2.34 at the comp median, 16 plans across 4 properties.
3BR
Pro forma $3,250 on 1,300 SF
No tracked West End property posts a three bedroom ask today. The row waits for a posted comp rather than inventing one.
Per square foot: $2.50 pro forma; no posted comp to quote; needs a sponsor comp.
Market concession observed: 4.33 weeks median across 3 of 4 properties; the pro forma carries 0.5% of gross potential rent (0.26 weeks on a 12-month lease) at stabilization and none in lease-up.
Median of base-rent weeks off at the 3 priced properties posting a stated offer; of the rest, 1 posts no concession. Effective rent is ask x (52 - weeks off) / 52 on a 12-month lease; garage and other non-rent offers do not change it. 1 offer reads "up to" and is taken at the stated maximum. The concession rate is the sponsor's input; this is a comparison, not advice.
Two different kinds of fact, stated as such. The comp side is asking rents read from 4 of 10 tracked West End properties' own websites on November 8, 2026, and asks are not effective rents: 3 of the 4 responding properties are running a concession. Our side is the pro forma's unit rents in today's dollars, the base the model grows at 3.00% a year to stabilization in month 36, on a building that has not been built. A reality check against the comp set the sponsor selected for this sample, not a projection.
Checked against comps:Tax compsLand comps
Business plan and schedule
- Units
- 200
- across four plans
- Average rent
- $2,184
- per unit per month
- Construction
- 23 mo
- start to complete
- Lease-up
- 11 mo
- first delivery to stabilized
- Studio3074.3
- 1BR80108.0
- 2BR75116.8
- 3BR15121.3
| Type | Units | Months to full | Units per month |
|---|---|---|---|
| Studio | 30 | 7 | 4.3 |
| 1BR | 80 | 10 | 8.0 |
| 2BR | 75 | 11 | 6.8 |
| 3BR | 15 | 12 | 1.3 |
| Building, from Feb 2029 | 200 | 11 | 18.2 |
Show the full sectionHide the full sectionFill by type, the building filling up, specifications, schedule and phases.
Fill by type
Each plan as a share of its own count.
About this card
The building, filling up
One square per unit, grouped by plan. Press play, or drag to any month.
189 of 200 occupied · 95% of what is builtstabilized
Specifications and amenities
The spec book, in the format a live deal publishes.
About this card
Unit interiors
- Countertops
- Quartz, 3 cm, eased edge, kitchens and baths
- Cabinets
- Flat panel, soft close, two tone scheme by floor
- Flooring
- Luxury vinyl plank throughout; porcelain tile at baths
- Appliances
- Stainless package, electric range, French door refrigerator, dishwasher, microwave
- Laundry
- Full size stacked washer and dryer in every unit
- Ceilings
- 9 feet typical; 10 feet on the top floor
- Windows
- Double pane vinyl, low E, solar shades in living rooms
- Smart features
- Keyless entry, smart thermostat, leak sensors at wet walls
Amenities
- Fitness
- 2,100 square feet, strength and cardio, on demand studio
- Rooftop terrace
- Grills, firepit lounge, downtown skyline orientation
- Coworking
- Eight seats, two call rooms, conference room by reservation
- Resident lounge
- Chef's kitchen, private dining, game wall
- Package
- Locker room with cold storage for grocery delivery
- Pets
- Dog run on the podium courtyard and a wash station
- Bikes
- Secured storage for 120 bikes with a repair stand
Building and systems
- Construction
- Four wood-framed stories over one concrete podium story with structured parking
- Parking
- 230 structured stalls; 46 EV ready
- Elevators
- Two traction cabs serving all floors
- Heating and cooling
- Individual electric heat pumps, unit by unit control
- Metering
- Electric metered to each unit; water submetered and reimbursed
- Connectivity
- Fiber to every unit, building wide managed wifi in amenity areas
- Roof
- TPO membrane, 20 year warranty, solar ready conduit runs
Services
- Trash
- Valet pickup five nights a week, chute per floor
- Access
- Fob and phone credentialed, cameras at entries and garage
- Management
- On site manager and maintenance, two person team at stabilization
Parking runs 230 stalls against 200 units, 1.15 per unit, and it is the same podium garage the parking income line and the building's footprint come from. Sample specifications, in the format a live spec book publishes.
Schedule
Closing to sale. Every month between milestones is modelled.
Closing
Jan 2027
month 0
Construction start
Feb 2027
month 1
Construction complete
Jan 2029
month 24
First delivery
Feb 2029
month 25
Stabilized
Jan 2030
month 36
Refinance
Feb 2032
month 61
Sale
Jan 2037
month 120
Construction
23 mo
start to complete
Lease-up
11 mo
first delivery to stabilized
Stabilized NOI
$3.8M
$18,936 per unit
Expense ratio
34.2%
of effective gross income
How this deal got here, and what is left
Seven phases, each ending in a dated gate.
About this card
The seven phases in detail: every gate, task, owner and cadence
Site control
month -14 to -11
Gate: Purchase agreement signed, diligence period open
A seller's willingness to wait. The diligence period has to be long enough to clear entitlement risk or the deposit goes hard on an unapproved site.
- Letter of intent · CountersignedSponsor
- Purchase agreement · ExecutedCounsel
- Diligence period and extensions · Dated in the PSACounsel
Feasibility
month -11 to -8
Gate: No condition found that kills the site
Geotechnical and environmental turnaround. Both are lab-bound and neither compresses for money.
- Survey and title commitment · Exceptions reviewedCounsel
- Geotechnical report · Borings returnedEngineer
- Phase I environmental · No recognized conditionConsultant
- Utility will-serve letters · Capacity confirmed in writingCivil
- Zoning and overlay review · Entitlement path identifiedLand use counsel
Entitlement
month -8 to -2
Gate: Approval recorded, appeal period run
The commission calendar, not the staff. Nine months of this phase is waiting for an agenda, which is why submittal dates matter more than drawing speed.
- Concept review with staff · Comments issuedLand use counsel
- Neighborhood meeting · Held and minutedSponsor
- Formal application · Deemed completeLand use counsel
- Planning commission · Recommendation carriedSponsor
- City council · ApprovedSponsor
- Appeal period · Expired without challengeCounsel
Design
month -8 to 0
Gate: Permit set submitted
Runs alongside entitlement rather than after it, which is the single biggest schedule saving available on a development deal and the one most often given away.
- Schematic design · Unit mix and massing fixedArchitect
- Design development · Systems selectedArchitect
- Construction documents · Issued for permitArchitect
- Guaranteed maximum price · Signed with the contractorContractor
Financing
month -5 to 0
Gate: Loan and equity close the same day as land
Lender credit committee and the equity raise, in parallel. Neither will close ahead of entitlement.
- Construction loan term sheet · AcceptedSponsor
- Equity raise · Subscriptions fundedSponsor
- Credit committee · Commitment issuedLender
- Closing · Land acquired, loan recordedCounsel
Construction
month 1 to 24
Gate: Certificate of occupancy, final
The building, and winter. A Minneapolis deal that misses its concrete window loses a season rather than a month.
- Notice to proceed · IssuedSponsor
- Foundations complete · InspectedContractor
- Topping out · Structure completeContractor
- First certificate of occupancy · First units deliverableCity
- Substantial completion · Punch list issuedContractor
Lease-up
month 25 to 36
Gate: Stabilized occupancy held for three months
Absorption by unit type. The slowest plan sets the date, not the average.
- Marketing and pre-leasing · Reservations takenProperty manager
- First move-ins · Rent commencesProperty manager
- Stabilization · Occupancy threshold metProperty manager
- Permanent loan readiness · Coverage seasoned for the month 61 refinanceSponsor
What repeats
The durations above are different on every deal. The cadences are not, and they are what turn a duration from a hope into arithmetic: nine submittals on a two-week review cycle is eighteen weeks whatever anyone wanted.
Owner, architect and contractorWeekly
The meeting that catches a coordination problem while it is still a drawing.
Planning commissionFirst and third Tuesday
Agenda closes ten working days out. Miss it and the next slot is a fortnight, not a day.
City councilEvery other Friday
Only hears items the commission has already recommended.
Lender drawMonthly
Inspection, then funding. The gap between the two is working capital.
Investor reportingQuarterly
Actual against projected, from the same record that produced the projection.
Budget: sources and uses
- Total cost
- $52.2M
- $260,945 per unit
- Hard costs
- $41.0M
- $205,000 per unit, 78.6%
- Land
- $2.0M
- $10,000 per unit
- Per square foot · total cost
- $164
- gross, $292 net rentable
- Hard costs$41,000,00078.6%
- Capitalized interest and loan fees$2,294,1704.4%
- Developer fee$2,040,0003.9%
- Land and acquisition$2,000,0003.8%
- City and government$1,600,0003.1%
- Design and consultants$1,221,0002.3%
- FF&E and pre-opening marketing$625,0001.2%
- Contingency and rounding$488,5100.9%
- Financing, title and closing$418,2700.8%
- Carry and pre-open operating$289,6480.6%
- Legal, accounting and equity$212,4030.4%
| Use | Amount | Per unit | Per NRSF | Share |
|---|---|---|---|---|
| Hard costs | $41,000,000 | $205,000 | $229.05 | 78.6% |
| Capitalized interest and loan fees | $2,294,170 | $11,471 | $12.82 | 4.4% |
| Developer fee | $2,040,000 | $10,200 | $11.40 | 3.9% |
| Land and acquisition | $2,000,000 | $10,000 | $11.17 | 3.8% |
| City and government | $1,600,000 | $8,000 | $8.94 | 3.1% |
| Design and consultants | $1,221,000 | $6,105 | $6.82 | 2.3% |
| FF&E and pre-opening marketing | $625,000 | $3,125 | $3.49 | 1.2% |
| Contingency and rounding | $488,510 | $2,443 | $2.73 | 0.9% |
| Financing, title and closing | $418,270 | $2,091 | $2.34 | 0.8% |
| Carry and pre-open operating | $289,648 | $1,448 | $1.62 | 0.6% |
| Legal, accounting and equity | $212,403 | $1,062 | $1.19 | 0.4% |
| Total uses | $52,189,000 | $260,945 | $291.56 | 100.0% |
Show the full sectionHide the full sectionSources, draws, debt balances, line-by-line attribution and basis.
Sources
Equity funds first, then the loan draws.
About this card
Loan to cost
65%
on drawn balance
Capitalized interest
$2.2M
into basis
One commitment stands behind the sources without appearing in them: the part of the lease-up deficit the reserve does not cover is the sponsor's to fund, with the figures in diligence answer three.
Uses, by section
The bar is each section's share of total project cost.
About this card
The draw schedule
When the money has to be there.
About this card
Capital is called at closing and then monthly against completed work, through month 15, when equity is exhausted and the loan takes over. Calls follow the curve above, not a schedule of round numbers.
Debt outstanding, by facility
Construction draws, retired at the refinance, then the permanent loan.
About this card
Where every dollar comes from and where it goes
Equity-first attribution, line by line, month by month.
About this card
Equity $18.3MConstruction loan $33.9M
Hard costs$41.0M
equity $11.8M · loan $29.2M
Capitalized interest and loan fees$2.3M
equity $413K · loan $1.9M
Developer fee$2.0M
equity $585K · loan $1.5M
Everything under 1.5% of cost (5 lines)$2.0M
equity $695K · loan $1.3M
Land and acquisition$2.0M
equity $2.0M · no loan
City and government$1.6M
equity $1.6M · no loan
Design and consultants$1.2M
equity $1.2M · no loan
Basis against replacement cost and recent trades
All-in cost to build, beside what it would cost to build the same building today and what comparable buildings have sold for. The comparison figures here are sample values; a live sponsor states them with sources.
- Basis per unit
- $260,945
- Per net rentable SF
- $292
- Per gross SF
- $164
- Replacement cost per unit
- $285,000
- Source
- Sponsor's estimate to build the same program on a comparable site today, land and soft costs included (sample)
- Basis against replacement
- -$24,055
Recent trades
Trade 1
- Property
- Sample: 186-unit podium, Minneapolis (sample)
- Date
- Mar 2026
- Units
- 186
- Price per unit
- $268,000
- Cap rate
- 5.10%
- Basis against the trade
- -$7,055
Trade 2
- Property
- Sample: 224-unit podium, Edina (sample)
- Date
- Nov 2025
- Units
- 224
- Price per unit
- $281,500
- Cap rate
- 4.95%
- Basis against the trade
- -$20,555
Trade 3
- Property
- Sample: 150-unit podium, Bloomington (sample)
- Date
- Jul 2025
- Units
- 150
- Price per unit
- $247,000
- Cap rate
- 5.30%
- Basis against the trade
- +$13,945
How the TIF works on this deal
- Base taxes stay with the cityBase taxes per yearSponsor to confirm
- New building raises the tax billProjected taxes per year$440,000
- The increment repays the TIF noteIncrement per yearSponsor to confirm
- The note reduces equity neededTIF note (not modeled)Sponsor to confirm
How the figures are sourced
- Projected taxes: units times real estate taxes per unit in the model.
- Base taxes and the increment come from the city's TIF analysis, not the model.
- The model carries TIF as an upfront source ahead of equity.
- Note terms, term length and any pay-as-you-go structure: sponsor to confirm.
Land and operating costs, checked:Land compsOperating expenses
Financing
- Construction loan
- $33.9M
- 65% of cost, interest only
- Construction rate · underwritten
- 7.00%
- 5.90% today, 7.25% capped
- Term
- 42 months
- 2 of 2 extensions neededfinal maturity month 66
- Permanent loan · month 61
- $47.0M
- $39.0M at the 7.15% stress
How the permanent loan is sized
Three tests; the binding one sets the loan.
At maximum loan to value
$48.2M
At minimum coverage
$47.0M
Binding: this is the loan
At the rate stress, 7.15%
$39.0M
Coverage binds here, at $47.0M. The refinance pays off $33.0M of construction debt and distributes $14.0M to equity. The model states a payoff of $32,982,304; the draw schedule carries the loan at $33,922,221 drawn (the $33,922,000 commitment plus $221 of draw rounding), interest only, with no stated paydown. The $939,916 difference is not explained by a stated line. Paid off at the drawn balance, the $47,032,000 loan less $25,000 of closing costs would distribute $13.1M, not $14.0M. The pro forma link settles it. The stress case prices the same coverage test at 7.15%, the 5.40% assumption plus 175 basis points, and sizes to $39.0M: the gap between the two loans is the exposure to rates between now and month 61.
Show the full sectionHide the full sectionBoth loans in full: rate, term, extensions, recourse and covenants.
Both loans, in full
Rate, term, amortization, extensions, recourse and covenants.
About this card
Construction loan
$33.9M
- Lender
- Sample Regional Bank, construction lending group, term sheet signed
- Rate
- Floating, SOFR plus 275 basis points, with a purchased cap at 4.50%. Underwritten at 7.00% all in: the cash flow's construction debt service is drawn at that rate, above today's 5.90% indication and below the 7.25% capped maximum
- Index
- SOFR, currently indicated at 3.15%
- Term
- 42 months from closing
- Amortization
- Interest only
- Extensions
- Two twelve-month extensions, each conditional on 1.15x coverage on trailing three months and a 25 basis point fee. Fully extended the loan reaches month 66, five months past the modelled refinance.
- Recourse
- Completion guarantee and standard non-recourse carve-outs from the sponsor principals. No repayment guarantee. Standing behind the completion guarantee alongside investors: the sponsor's own $548,045 co-investment, 3.0% of the equity.
- Prepayment
- Open after month 18, no penalty
- Covenants
- 1.20x minimum debt service coverage from stabilization
- In-balance test at each draw
- Minimum liquidity and net worth on the guarantors, with the figures set in the loan agreement; this sample does not fix them
Base case requires both extensions (months 42 and 54)
- Extension 1, month 42: fee25 bp on $33,922,221 outstanding
- $84,806
- Extension 1: projected trailing 3-month coveragetest 1.15x, passes
- 1.60x
- Extension 2, month 54: fee25 bp on $33,922,221 outstanding
- $84,806
- Extension 2: projected trailing 3-month coveragetest 1.15x, passes
- 1.64x
- Extension fees, totalNot in the cash flow or the uses
- $169,611
- Fully extended maturity5 months past the month 61 refinance
- month 66
Floating. The cap strike of 4.50% is 135 basis points above the indicated index, so the first 135 basis points of any rate move is carried by the deal and not by the cap.
Permanent loan
$47.0M
- Lender
- Not yet engaged: agency or life company execution assumed at month 61
- Rate
- Assumed at 5.40% fixed
- Term
- 10 years from funding in month 61
- Amortization
- 30 years
- Extensions
- None
- Recourse
- Non-recourse with standard carve-outs
- Prepayment
- Yield maintenance to year seven, open thereafter
- Covenants
- 1.20x minimum debt service coverage, tested annually
This is a forecast of a rate five years out, not a commitment. It is the single most consequential undisclosed assumption on most deal pages: the whole refinance distribution rests on it, and at 6.50% instead the loan sizes to roughly $41.6M and the month 61 distribution falls from $14.0M to about $8.6M.
The refinance payoff, against the drawn balance
- Drawn construction balance, interest onlyFrom the draw schedule, carried to the refinance
- $33,922,221
- Payoff stated in the workbook
- $32,982,304
- Variance, a named seamNo stated line pays the loan down; neither figure is changed here
- $939,916
- Net proceeds, as stated
- $14,024,696
- Net proceeds if the payoff is the drawn balance
- $13,084,779
- Refinance transaction costs, sponsor inputSource: none yet; as of: none yet. Lender, title, legal and third-party costs of the month 61 refinance. Deducted from net proceeds once the sponsor states them.
- Not stated
- Net proceeds after entered costs
- $14,024,696
Projected cash flow
- Untrended yield on cost
- 6.5%
- at today's rents and costs
- Trended yield on cost
- 7.3%
- after 3 years of rent growth
- Net to all equity, before the split
- $38.2M
- distributions less contributions over 10 years; investors receive $49.9M gross after the split
- Year 10 cash to equity
- $36.2M
- includes net sale proceeds
Show the full sectionHide the full sectionRevenue build, untrended against trended, and the ten-year table.
How rent becomes income
Gross potential rent to effective gross income, today and stabilized.
About this card
Gross potential rent is every unit at its asking rent for twelve months, derived from the mix rather than entered: 200 units at $2,184 blended, which is $5,241,000 a year. Every deduction below is a stated rate applied identically to both columns. The two differ by 3 years of rent growth at 3.0% and nothing else.
All figures in dollars, annual
| Line | Rate | At today's rents | First stabilized year, as projected |
|---|---|---|---|
| Gross potential rent | every unit at its asking rent, twelve months | 5,241,000 | 5,726,982 |
| Loss to lease | none: a new building has no leases below market | – | – |
| Vacancy | 5.0% of gross potential | (262,050) | (286,349) |
| Rent billed | 4,978,950 | 5,440,633 | |
| Concessions | 0.5% of gross potential | (26,205) | (28,635) |
| Credit loss | 0.4% of rent billed | (19,916) | (21,763) |
| Net rental income | 4,932,829 | 5,390,236 | |
| Utility reimbursement | 120,654 | 131,842 | |
| Parking | 164,223 | 179,451 | |
| Storage, pet and other | 50,272 | 54,934 | |
| Effective gross income | 5,267,979 | 5,756,463 |
- Gross potential rentevery unit at its asking rent, twelve months
- 5,241,000
- 5,726,982
- Loss to leasenone: a new building has no leases below market
- –
- –
- Vacancy5.0% of gross potential
- (262,050)
- (286,349)
- Rent billed
- 4,978,950
- 5,440,633
- Concessions0.5% of gross potential
- (26,205)
- (28,635)
- Credit loss0.4% of rent billed
- (19,916)
- (21,763)
- Net rental income
- 4,932,829
- 5,390,236
- Utility reimbursement
- 120,654
- 131,842
- Parking
- 164,223
- 179,451
- Storage, pet and other
- 50,272
- 54,934
- Effective gross income
- 5,267,979
- 5,756,463
Other income is $153 per unit per month at stabilization across utility reimbursement, parking and storage. On a podium building with structured parking that sits inside convention, which is roughly $120 to $185. It is the one line here carried as a residual rather than a rate, and on a live deal it is a sponsor input with a source rather than a plug.
Break-even, in both debt regimes, at both thresholds
Before the refinance
After the refinance
Two thresholds. At 1.00x the building covers its bills: after the refinance that takes $2,150 against today's asking of $2,184, so rents can fall below today and the loan is still paid. The covenant is the stricter line a lender tests, and the margin there is thinner: the permanent loan is sized at 1.20x on income five years out, so at the covenant it needs $2,430, above today's asking. The margin depends on rent growth between now and month 61; a loan sized at its covenant has no covenant margin on the day it funds.
Before any rent growth, and after
The same building, cost and cap rate, three years apart. The difference is projected rent growth.
- Effective gross income
- 5,267,979
- Operating expenses
- (1,482,000)
- Property tax
- (386,000)
- Net operating income
- 3,399,979
Untrended yield on cost
6.5%
Value at 5.25%
$64.8M
- Effective gross income
- 5,756,463
- Operating expenses
- (1,561,286)
- Property tax
- (408,000)
- Net operating income
- 3,787,177
Trended yield on cost
7.3%
Value at 5.25%
$72.1M
The two sides differ by 3 years of rent growth and nothing else: the same building, the same cost, the same 5.25% cap rate. That gap is $387K of annual income, worth $7.4M of value, and it is the part of the case that depends on a market rather than on the building. A deal that only works trended is a bet on rent growth; this one clears 6.5% on cost before any growth at all.
Ten-year cash flow
Years from closing; the last two rows are the split.
About this card
All figures in dollars
| Year ending | 1Construction | 2Construction | 3Lease-up | 4First stabilized year | 5Operating | 6Refinance | 7Operating | 8Operating | 9Operating | 10Sale |
|---|---|---|---|---|---|---|---|---|---|---|
| Average occupancy | – | – | 45.7% | 94.6% | 94.6% | 94.6% | 94.6% | 94.6% | 94.6% | 94.6% |
| Effective gross income | – | – | 2,484,000 | 5,756,463 | 5,898,000 | 6,045,000 | 6,196,000 | 6,351,000 | 6,510,000 | 6,672,000 |
| Operating expenses | – | – | (969,000) | (1,561,286) | (1,598,143) | (1,637,097) | (1,677,625) | (1,719,665) | (1,763,157) | (1,806,036) |
| Property tax | – | – | (381,000) | (408,000) | (418,000) | (429,000) | (440,000) | (451,000) | (462,000) | (474,000) |
| Net operating income | – | – | 1,134,000 | 3,787,177 | 3,881,857 | 3,978,903 | 4,078,375 | 4,180,335 | 4,284,843 | 4,391,964 |
| Capital reserve | – | – | (50,000) | (100,000) | (102,500) | (105,060) | (107,687) | (110,379) | (113,138) | (115,966) |
| Debt service | – | – | (2,374,000) | (2,374,000) | (2,374,000) | (3,155,981) | (3,155,981) | (3,155,981) | (3,155,981) | (3,155,981) |
| Capital event | (13,272,070) | (4,994,709) | – | – | – | 14,024,696 | – | – | – | 35,121,834 |
| Cash to equity | (13,272,070) | (4,994,709) | (1,290,000) | 1,313,177 | 1,405,357 | 14,742,558 | 814,707 | 913,975 | 1,015,724 | 36,241,851 |
| To investors | – | – | – | 1,313,177 | 1,405,357 | 14,742,558 | 814,707 | 913,975 | 1,015,724 | 28,787,743 |
| To the sponsor | – | – | – | – | – | – | – | – | – | 7,454,108 |
All figures in dollars, one block per year
Year 1Construction
- Average occupancy
- –
- Effective gross income
- –
- Operating expenses
- –
- Property tax
- –
- Net operating income
- –
- Capital reserve
- –
- Debt service
- –
- Capital event
- (13,272,070)
- Cash to equity
- (13,272,070)
- To investors
- –
- To the sponsor
- –
Year 2Construction
- Average occupancy
- –
- Effective gross income
- –
- Operating expenses
- –
- Property tax
- –
- Net operating income
- –
- Capital reserve
- –
- Debt service
- –
- Capital event
- (4,994,709)
- Cash to equity
- (4,994,709)
- To investors
- –
- To the sponsor
- –
Year 3Lease-up
- Average occupancy
- 45.7%
- Effective gross income
- 2,484,000
- Operating expenses
- (969,000)
- Property tax
- (381,000)
- Net operating income
- 1,134,000
- Capital reserve
- (50,000)
- Debt service
- (2,374,000)
- Capital event
- –
- Cash to equity
- (1,290,000)
- To investors
- –
- To the sponsor
- –
Funded by the lease-up reserve ($100,868) and a sponsor commitment ($1,139,132) for the $1,240,000 operating deficit; funding for the $50,000 capital reserve deposit is not stated. Not investor capital, so not in the net to equity.Year 4First stabilized year
- Average occupancy
- 94.6%
- Effective gross income
- 5,756,463
- Operating expenses
- (1,561,286)
- Property tax
- (408,000)
- Net operating income
- 3,787,177
- Capital reserve
- (100,000)
- Debt service
- (2,374,000)
- Capital event
- –
- Cash to equity
- 1,313,177
- To investors
- 1,313,177
- To the sponsor
- –
Year 5Operating
- Average occupancy
- 94.6%
- Effective gross income
- 5,898,000
- Operating expenses
- (1,598,143)
- Property tax
- (418,000)
- Net operating income
- 3,881,857
- Capital reserve
- (102,500)
- Debt service
- (2,374,000)
- Capital event
- –
- Cash to equity
- 1,405,357
- To investors
- 1,405,357
- To the sponsor
- –
Year 6Refinance
- Average occupancy
- 94.6%
- Effective gross income
- 6,045,000
- Operating expenses
- (1,637,097)
- Property tax
- (429,000)
- Net operating income
- 3,978,903
- Capital reserve
- (105,060)
- Debt service
- (3,155,981)
- Capital event
- 14,024,696
- Cash to equity
- 14,742,558
- To investors
- 14,742,558
- To the sponsor
- –
Year 7Operating
- Average occupancy
- 94.6%
- Effective gross income
- 6,196,000
- Operating expenses
- (1,677,625)
- Property tax
- (440,000)
- Net operating income
- 4,078,375
- Capital reserve
- (107,687)
- Debt service
- (3,155,981)
- Capital event
- –
- Cash to equity
- 814,707
- To investors
- 814,707
- To the sponsor
- –
Year 8Operating
- Average occupancy
- 94.6%
- Effective gross income
- 6,351,000
- Operating expenses
- (1,719,665)
- Property tax
- (451,000)
- Net operating income
- 4,180,335
- Capital reserve
- (110,379)
- Debt service
- (3,155,981)
- Capital event
- –
- Cash to equity
- 913,975
- To investors
- 913,975
- To the sponsor
- –
Year 9Operating
- Average occupancy
- 94.6%
- Effective gross income
- 6,510,000
- Operating expenses
- (1,763,157)
- Property tax
- (462,000)
- Net operating income
- 4,284,843
- Capital reserve
- (113,138)
- Debt service
- (3,155,981)
- Capital event
- –
- Cash to equity
- 1,015,724
- To investors
- 1,015,724
- To the sponsor
- –
Year 10Sale
- Average occupancy
- 94.6%
- Effective gross income
- 6,672,000
- Operating expenses
- (1,806,036)
- Property tax
- (474,000)
- Net operating income
- 4,391,964
- Capital reserve
- (115,966)
- Debt service
- (3,155,981)
- Capital event
- 35,121,834
- Cash to equity
- 36,241,851
- To investors
- 28,787,743
- To the sponsor
- 7,454,108
- Year 1Equity drawn for land and early construction
- Year 2Remaining equity drawn
- Year 3Lease-up deficit: the reserve covers part, a sponsor commitment funds the rest (diligence 3)
- Year 6Net refinance proceeds returned to investors
- Year 10Net sale proceeds
- Year 3 cashFunded by the lease-up reserve ($100,868) and a sponsor commitment ($1,139,132) for the $1,240,000 operating deficit; funding for the $50,000 capital reserve deposit is not stated. Not investor capital, so not in the net to equity.
Net to all equity, before the split$38.2M
Returns
- Project, unlevered
- 10.27%
- before any debt
- Project, levered
- 16.85%
- 3.14x before the split
- Investor
- 15.16%
- 2.73x after the split
- Sponsor
- 37.24%
- $7.5M promote, earned last
Show the full sectionHide the full sectionThe dollar journey, return bridge, profit sources, and sale-year returns.
One investor's $100,000, start to finish
The deal in four stops, at the investor multiple.
- 1
Years 1 to 2
Your money builds the building
Capital is called as construction is paid for. Equity goes into the ground first, before the lender funds anything.
- 2
Years 3 to 4
The building fills and distributions begin
An 8% preferred return accrues from the day capital is funded. Whatever a year does not pay in cash is deferred, not forgiven.
- 3
Year 6
The refinance distributes cash to investors
The permanent loan pays off construction debt and distributes $14.0M: about $7.7M returns capital and about $7.0M pays accrued preferred return. Unreturned capital stays invested until the sale.
- 4
Year 10
The sale completes the return
The building sells, the loan is repaid, and the balance of capital and profit distributes through the waterfall.
IRR, multiple, cash-on-cash and distribution mix, defined and computed.How this is calculated
Where the money comes back from, at the project level
Three events: operations, an early refinance, and the sale.
About this card
Investedat closing and during construction-$18.3M
Operationsacross the hold$8.2M
Refinancemonth 61$14.0M
Salemonth 120$35.1M
Net gain2.14x gain, 3.14x back$39.1M
The month 61 refinance distributes $14.0M, about $7.7M of it capital and about $7.0M accrued preferred return. Cash returned before the sale raises the IRR relative to the same dollars arriving at the sale.
The split
What the project earns, and how it divides.
The sponsor earns a promote only after investors have their capital back and their preferred return. The gap between the levered project return and the investor return reflects the promote, the sponsor's fees, and the sponsor's pari passu return on its co-investment.
- Sponsor co-investment
- $548K
- 3.0% of equity, pari passu with investors
- Refinance distribution, month 61
- $14.0M
- about $7.7M capital, about $7.0M accrued preferred return
- Untrended yield on cost
- 6.51%
- At today's rents and costs. 7.26% trended to stabilization.
Sensitivity
One result across two drivers, around the base case. The sponsor chooses the grid.
LP IRR by exit cap and rent growth after year 4, the sponsor's projection.
Base case: 5.50% exit cap, 2.50% rent growth after year 4, LP IRR 15.16%, the model's figure; other cells add the change from the model's base
LowHigh
| Exit cap / Rent growth after year 4 | 1.50% | 2.00% | 2.50% | 3.00% | 3.50% |
|---|---|---|---|---|---|
| 5.00% | 14.85% | 15.84% | 16.77% | 17.60% | 18.36% |
| 5.25% | 13.98% | 14.99% | 15.96% | 16.88% | 17.67% |
| 5.50% | 13.14% | 14.18% | 15.16%Base | 16.10% | 17.00% |
| 5.75% | 12.31% | 13.38% | 14.39% | 15.35% | 16.27% |
| 6.00% | 11.50% | 12.60% | 13.64% | 14.62% | 15.56% |
Sources of profit
Cash flow, loan paydown, and value created. The three sum to the project profit.
The building pays cash
$8.2M
21.0% of the profit
Rent, less expenses, less the loan payment. Collected across the hold and paid as distributions.
The tenants pay the loan down
$3.8M
9.7% of the profit
The permanent loan amortizes from year six. Every payment the rent makes shifts a little of the building from the bank to the owners.
The building is worth more than it cost
$27.1M
69.4% of the profit
Built for less than finished buildings trade for, then sold. Most of this is the development spread, earned by building, not by waiting for a market. Net of the costs of selling.
A deal leaning mostly on the first two engines is carried by the building; one leaning on the third is carried by the exit. Most of this deal's third engine is the development spread, earned by building at a cost below what finished buildings trade for, not a bet on the market improving.
Return by year of sale
The annual return and the multiple if the building sold in each year of the hold.
Annual return if sold that year
Multiple on the money if sold that year
The rate peaks the year the building is finished and falls every year after, because the development profit is earned by building and each further year dilutes it with operating returns. The multiple climbs the whole way, because money keeps arriving. Which end of this chart an investor prefers depends on what their capital would otherwise do, which is exactly why the page shows both instead of picking one. A constant 5.50% exit cap in every year, the deal's own 0.86% costs of sale, the next year's income over the cap, and that month's loan balance repaid. Project level, before the split.
Tax programs (opportunity zone, depreciation) and the capital gains comparison.How this is calculated
Distribution waterfall
- Preferred return
- 8%
- accrues, compounds annually
- To investors over the hold
- $49.9M
- 2.73 times capital, on all $18.3M of equity, the sponsor's co-investment included
- Sponsor promote
- $7.5M
- earned last
- Sponsor co-investment
- $548K
- pari passu with investors
- 1. Preferred return100%0%
- 2. Return of capital100%0%
- 3. Sponsor catch-up50%50%
- 4. Residual to a 15% investor return80%20%
- 5. Residual above a 15% investor return70%30%
| Tier | Until | Investors | Sponsor | Details |
|---|---|---|---|---|
| 1. Preferred return | Until investors have received an 8% annual return on unreturned capital | 100% | 0% | |
| 2. Return of capital | Until investors have received all contributed capital back | 100% | 0% | |
| 3. Sponsor catch-up | Until the sponsor has received 20% of profit distributed to that point | 50% | 50% | |
| 4. Residual to a 15% investor return | Until investors have received a 15% annual return | 80% | 20% | |
| 5. Residual above a 15% investor return | All remaining proceeds | 70% | 30% |
Tier 1: Preferred return
Until investors have received an 8% annual return on unreturned capital
- To investors
- 100%
- To the sponsor
- 0%
Accrues from the date capital is funded and compounds annually. Unpaid preferred return rolls forward rather than lapsing, so a year without a distribution is deferred, not forgiven.
Tier 2: Return of capital
Until investors have received all contributed capital back
- To investors
- 100%
- To the sponsor
- 0%
The refinance in month 61 is the first event large enough to return capital. Until this tier closes the sponsor earns no promote at all.
Tier 3: Sponsor catch-up
Until the sponsor has received 20% of profit distributed to that point
- To investors
- 50%
- To the sponsor
- 50%
A 50/50 catch-up rather than a 100/0. The sponsor reaches its 20% more slowly, and investors keep receiving cash throughout the tier instead of pausing.
Tier 4: Residual to a 15% investor return
Until investors have received a 15% annual return
- To investors
- 80%
- To the sponsor
- 20%
The tier the base case lands inside. The projected investor return of 15.16% sits a fraction above the hurdle, so most of the promote is earned here.
Tier 5: Residual above a 15% investor return
All remaining proceeds
- To investors
- 70%
- To the sponsor
- 30%
Only reached if the deal outperforms. Nothing in the base case is distributed in this tier.
Show the full sectionHide the full sectionThe tiers by year, at the sale, partnership terms and the agreement.
Distributions by tier, over the hold
Money through each tier over the hold, on one scale.
About this card
Investors put in $18.3Mand over ten years the deal pays $56.4M back to equity. Every dollar walks down the same staircase.
To investorsTo the sponsorWaterfall arithmetic only: every distribution scaled by one factor, the five rules rerun. What rents or the exit do to the cash is the sponsor's model, not this chart.
Everything distributed
Operating cash, the refinance, and the sale, all ten years
1 · Preferred return
Until investors have received an 8% annual return on unreturned capital
$13.2M investors · sponsor $0
2 · Return of capital
Until investors have received all contributed capital back
$18.3M investors · sponsor $0
$43.3M spills on to this tier
3 · Sponsor catch-up
Until the sponsor has received 20% of profit distributed to that point
$4.4M investors · $4.4M sponsor
$25.0M spills on to this tier
4 · Residual to a 15% investor return
Until investors have received a 15% annual return
$13.2M investors · $3.1M sponsor
$16.2M spills on to this tier
The money runs out 64% into this tier. Clearing it would take $9.2M more.
5 · Residual above a 15% investor return
All remaining proceeds
Where it lands
The same $56.4M, summed by who keeps it
Investors keep 87% of everything distributed. The sponsor's $7.5M arrives entirely in year ten, at the sale, after investors have collected an 8% preferred return, every dollar of capital back, and the first $31.4M the deal ever distributes. Navy is all equity, including the sponsor's own co-investment returned pari passu; orange is the promote alone, run through the tier rules.
More waterfall viewsThe same five tiers by year, and the sale day from the closing table down.
The waterfall, year by year
One bar per year, segmented in tier order.
About this card
Years one to three distribute nothing: the building is being built. From year four, every bar is that year's cash in the order the tiers take it.
To investorsTo the sponsorYear 4
operations
$1.3M
Year 5
operations
$1.4M
Year 6
the refinance
$14.7M
Year 7
operations
$0.8M
Year 8
operations
$0.9M
Year 9
operations
$1.0M
Year 10
the sale
$36.2M
Operating years pay into tier one without closing it, because the preferred return accrues faster than small years can pay it down: unpaid pref rolls forward. The refinance in year six is the first event that reaches tier two, returning $7.7M of capital, and the sale is the only event that reaches tiers three and four, which is why every orange pixel on this chart sits in the final bar.
The sale, from the closing table down
The sale price, from the lender down through the tiers.
About this card
The building sells in month 120 for $80.0MThe final year moves $81.1M in all: the price, plus $1.1M of that year's operating cash. Here is that day, top to bottom.
Everything on the table
The sale price and the final year's operating cash
The permanent loan is repaid
No equity dollar moves before the lender is whole
Costs of sale
Broker, transfer and legal, 2.0% of the price
$37.8M continues
Tier 1 · Preferred return
The unpaid balance accrued through year nine, cleared here
$0.8M investors · sponsor $0
$36.2M reaches equity
Tier 2 · Return of capital
The capital still out after the refinance, every dollar of it back
$10.4M investors · sponsor $0
$35.4M continues
Tier 3 · Sponsor catch-up
50 / 50 until the sponsor holds 20% of profit distributed
$4.4M investors · $4.4M sponsor
$25.0M continues
Tier 4 · Residual to a 15% investor return
80 / 20 toward a 15% investor return
$13.2M investors · $3.1M sponsor
$16.2M continues
The day ends 64% into this tier. Filling it would take $9.2M more.
The summary
The same $81.1M, by who keeps it
Lender $43.3M · costs of sale $1.6M · investors $28.8M · sponsor $7.5M
This is the day the promote exists: every sponsor profit dollar in the deal, $7.5M, arrives in this column, after the lender's $43.3M, after the costs, after the last of the preferred return and all remaining capital. Ten years of work, settled in one closing.
Partnership terms Removal, clawback, key person, default and transfer.
Partnership terms
The limited partnership agreement governs. Each line is the sponsor's statement with the section it comes from; nothing here is a summary written by Apolis.
General partner removal, for cause
What counts as cause, who votes, and the vote required.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
General partner removal, without cause
Whether it is available, the vote required, and what the removed partner keeps.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
Clawback
Whether promote paid early is returned if later results fall short, and how it is secured.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
Key person
Who the key persons are and what happens if one leaves.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
Capital call default
What happens to an investor who misses a capital call.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
Transfer rights
Whether and how an investor may transfer an interest, and who must consent.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
Reporting
What investors receive, how often, and by when after period end.
- Sponsor statement
- Sponsor input, not stated
- LPA section
- [LPA SECTION]
| Term | What the sponsor states | Sponsor statement | LPA section |
|---|---|---|---|
| General partner removal, for cause | What counts as cause, who votes, and the vote required. | Sponsor input, not stated | [LPA SECTION] |
| General partner removal, without cause | Whether it is available, the vote required, and what the removed partner keeps. | Sponsor input, not stated | [LPA SECTION] |
| Clawback | Whether promote paid early is returned if later results fall short, and how it is secured. | Sponsor input, not stated | [LPA SECTION] |
| Key person | Who the key persons are and what happens if one leaves. | Sponsor input, not stated | [LPA SECTION] |
| Capital call default | What happens to an investor who misses a capital call. | Sponsor input, not stated | [LPA SECTION] |
| Transfer rights | Whether and how an investor may transfer an interest, and who must consent. | Sponsor input, not stated | [LPA SECTION] |
| Reporting | What investors receive, how often, and by when after period end. | Sponsor input, not stated | [LPA SECTION] |
The tiers walked through as a hundred dollars, comparison deals, and alternative waterfall structures.How this is calculated
The tiers, as the agreement states them each tier's test, split, and the clawback
Preferred return
8%
Accrues, compounds annually
Sponsor co-investment
$548K
3.0% of equity, alongside investors
Investor capital
$17.7M
97.0% of equity
1Preferred return
100%investor / sponsorUntil investors have received an 8% annual return on unreturned capital
Accrues from the date capital is funded and compounds annually. Unpaid preferred return rolls forward rather than lapsing, so a year without a distribution is deferred, not forgiven.
2Return of capital
100%investor / sponsorUntil investors have received all contributed capital back
The refinance in month 61 is the first event large enough to return capital. Until this tier closes the sponsor earns no promote at all.
3Sponsor catch-up
50%50%investor / sponsorUntil the sponsor has received 20% of profit distributed to that point
A 50/50 catch-up rather than a 100/0. The sponsor reaches its 20% more slowly, and investors keep receiving cash throughout the tier instead of pausing.
4Residual to a 15% investor return
80%20%investor / sponsorUntil investors have received a 15% annual return
The tier the base case lands inside. The projected investor return of 15.16% sits a fraction above the hurdle, so most of the promote is earned here.
5Residual above a 15% investor return
70%30%investor / sponsorAll remaining proceeds
Only reached if the deal outperforms. Nothing in the base case is distributed in this tier.
Clawback
Tested at final liquidation. If the sponsor has received promote in excess of what the realised results support, it is repaid to investors before the partnership closes.
If more capital is needed
Called pro rata on fourteen days' notice. An investor who does not fund is diluted on the formula set out in the operating agreement, not at the sponsor's discretion, and the dilution is capped at 1.5 times the shortfall.
Risks and downside cases
- Investor return, as modeled
- 15.2%
- center of the grid
- Worst corner of the grid
- 4.3%
- rent -9%, exit cap 6.25%
- Lease-up deficit
- $1.2M
- against a $101K reserve
- Coverage covenant
- 1.20x
- net operating income over debt service
Show the full sectionHide the full sectionThe rent and cap grid, downside cases, and covenant coverage.
Investor return, rent crossed with exit cap
One block per market rent case, exit cap rate on each cell. Green clears 12.0%, red does not. The outlined cell is the deal as drawn.
Market rent: -9%
- 4.75%
- 13.0%
- 5.00%
- 11.6%
- 5.25%
- 10.1%
- 5.50%
- 8.7%
- 5.75%
- 7.2%
- 6.00%
- 5.8%
- 6.25%
- 4.3%
Market rent: -6%
- 4.75%
- 15.2%
- 5.00%
- 13.7%
- 5.25%
- 12.3%
- 5.50%
- 10.8%
- 5.75%
- 9.4%
- 6.00%
- 7.9%
- 6.25%
- 6.5%
Market rent: -3%
- 4.75%
- 17.4%
- 5.00%
- 15.9%
- 5.25%
- 14.5%
- 5.50%
- 13.0%
- 5.75%
- 11.6%
- 6.00%
- 10.1%
- 6.25%
- 8.7%
Market rent: As modeled
- 4.75%
- 19.5%
- 5.00%
- 18.1%
- 5.25%
- 16.6%
- 5.50%
- 15.2%
- 5.75%
- 13.7%
- 6.00%
- 12.3%
- 6.25%
- 10.8%
Market rent: +3%
- 4.75%
- 21.7%
- 5.00%
- 20.2%
- 5.25%
- 18.8%
- 5.50%
- 17.3%
- 5.75%
- 15.9%
- 6.00%
- 14.4%
- 6.25%
- 13.0%
Market rent: +6%
- 4.75%
- 23.8%
- 5.00%
- 22.4%
- 5.25%
- 20.9%
- 5.50%
- 19.5%
- 5.75%
- 18.0%
- 6.00%
- 16.6%
- 6.25%
- 15.1%
Market rent: +9%
- 4.75%
- 26.0%
- 5.00%
- 24.5%
- 5.25%
- 23.1%
- 5.50%
- 21.6%
- 5.75%
- 20.2%
- 6.00%
- 18.7%
- 6.25%
- 17.3%
| Market rent | 4.75% | 5.00% | 5.25% | 5.50% | 5.75% | 6.00% | 6.25% |
|---|---|---|---|---|---|---|---|
| -9% | 13.0% | 11.6% | 10.1% | 8.7% | 7.2% | 5.8% | 4.3% |
| -6% | 15.2% | 13.7% | 12.3% | 10.8% | 9.4% | 7.9% | 6.5% |
| -3% | 17.4% | 15.9% | 14.5% | 13.0% | 11.6% | 10.1% | 8.7% |
| As modeled | 19.5% | 18.1% | 16.6% | 15.2% | 13.7% | 12.3% | 10.8% |
| +3% | 21.7% | 20.2% | 18.8% | 17.3% | 15.9% | 14.4% | 13.0% |
| +6% | 23.8% | 22.4% | 20.9% | 19.5% | 18.0% | 16.6% | 15.1% |
| +9% | 26.0% | 24.5% | 23.1% | 21.6% | 20.2% | 18.7% | 17.3% |
The investor return is above an illustrative 12% allocator screen across most of this grid. It falls below the screen when rents miss by more than six percent and the exit cap widens at the same time.
Downside: overrun, delay, capital loss, refinance stress
What investors are projected to receive if the building costs more, finishes later, or sells into a weaker market, and what the refinance sizes to if rates rise.
Illustrative sensitivity, not the modelStraight lines from the headline case: each 5% of cost overrun takes 1.5 points off the investor IRR, each 3 months of delay takes 1.0 point, each 1% of rent below the model takes 0.72 points, each 25 bp of exit cap takes 1.45 points, and the multiple falls 0.11x for every point of IRR lost.
Investor IRR and multiple, cost overrun by construction delay
On budget
- On schedule
- 15.16%, 2.73x
- 3 months late
- 14.16%, 2.62x
- 6 months late
- 13.16%, 2.51x
- 9 months late
- 12.16%, 2.40x
+5% cost
- On schedule
- 13.66%, 2.57x
- 3 months late
- 12.66%, 2.46x
- 6 months late
- 11.66%, 2.35x
- 9 months late
- 10.66%, 2.24x
+10% cost
- On schedule
- 12.16%, 2.40x
- 3 months late
- 11.16%, 2.29x
- 6 months late
- 10.16%, 2.18x
- 9 months late
- 9.16%, 2.07x
+15% cost
- On schedule
- 10.66%, 2.24x
- 3 months late
- 9.66%, 2.13x
- 6 months late
- 8.66%, 2.02x
- 9 months late
- 7.66%, 1.91x
Capital-loss case: Exit cap +150 bp and rents -10%
- Investor IRR
- -0.74%
- Multiple
- 0.98x
- Investors get back
- $17.9Mof $18.3M
- Capital lost
- $332K
Same rule as the grid, both moves at once. Illustrative sensitivity, not the model.
Refinance at the 7.15% rate stress, month 61
- Loan as sized
- $47.0M
- Loan at the stress
- $39.0M
- Smaller by
- $8.1M
- Construction payoff
- $33.0M
The same coverage test priced at the stressed rate, from the loan sizing in the capital section. At the stress the loan still repays the construction loan; the smaller loan reduces what the refinance distributes to equity.
Coverage against the covenant
Net operating income over debt service, every month with debt service.
About this card
The lease-up deficit, and who funds it
Months 25 to 36: debt service less net operating income. A negative month is a surplus that pays part of it back. The first surplus month is month 33.
| Month | Occupancy | NOI | Debt service | Deficit | Cumulative |
|---|---|---|---|---|---|
| 25 | 1.0% | ($82,194) | $197,833 | $280,028 | $280,028 |
| 26 | 4.0% | ($70,216) | $197,833 | $268,049 | $548,077 |
| 27 | 9.1% | ($50,252) | $197,833 | $248,085 | $796,162 |
| 28 | 16.2% | ($22,302) | $197,833 | $220,135 | $1,016,298 |
| 29 | 25.3% | $13,633 | $197,833 | $184,200 | $1,200,498 |
| 30 | 36.4% | $57,554 | $197,833 | $140,279 | $1,340,777 |
| 31 | 49.5% | $109,461 | $197,833 | $88,372 | $1,429,149 |
| 32 | 60.3% | $152,188 | $197,833 | $45,645 | $1,474,794 |
| 33 | 72.6% | $200,613 | $197,833 | ($2,779) | $1,472,015 |
| 34 | 86.3% | $254,734 | $197,833 | ($56,901) | $1,415,114 |
| 35 | 93.5% | $283,151 | $197,833 | ($85,318) | $1,329,796 |
| 36 | 94.6% | $287,630 | $197,833 | ($89,796) | $1,240,000 |
Month 25
- Occupancy
- 1.0%
- NOI
- ($82,194)
- Debt service
- $197,833
- Deficit
- $280,028
- Cumulative
- $280,028
Month 26
- Occupancy
- 4.0%
- NOI
- ($70,216)
- Debt service
- $197,833
- Deficit
- $268,049
- Cumulative
- $548,077
Month 27
- Occupancy
- 9.1%
- NOI
- ($50,252)
- Debt service
- $197,833
- Deficit
- $248,085
- Cumulative
- $796,162
Month 28
- Occupancy
- 16.2%
- NOI
- ($22,302)
- Debt service
- $197,833
- Deficit
- $220,135
- Cumulative
- $1,016,298
Month 29
- Occupancy
- 25.3%
- NOI
- $13,633
- Debt service
- $197,833
- Deficit
- $184,200
- Cumulative
- $1,200,498
Month 30
- Occupancy
- 36.4%
- NOI
- $57,554
- Debt service
- $197,833
- Deficit
- $140,279
- Cumulative
- $1,340,777
Month 31
- Occupancy
- 49.5%
- NOI
- $109,461
- Debt service
- $197,833
- Deficit
- $88,372
- Cumulative
- $1,429,149
Month 32
- Occupancy
- 60.3%
- NOI
- $152,188
- Debt service
- $197,833
- Deficit
- $45,645
- Cumulative
- $1,474,794
Month 33
- Occupancy
- 72.6%
- NOI
- $200,613
- Debt service
- $197,833
- Deficit
- ($2,779)
- Cumulative
- $1,472,015
Month 34
- Occupancy
- 86.3%
- NOI
- $254,734
- Debt service
- $197,833
- Deficit
- ($56,901)
- Cumulative
- $1,415,114
Month 35
- Occupancy
- 93.5%
- NOI
- $283,151
- Debt service
- $197,833
- Deficit
- ($85,318)
- Cumulative
- $1,329,796
Month 36
- Occupancy
- 94.6%
- NOI
- $287,630
- Debt service
- $197,833
- Deficit
- ($89,796)
- Cumulative
- $1,240,000
Net over the twelve months, as stated: $1,240,000. The running shortfall peaks at $1,474,794 in month 32, so the commitment has to be available for $1,373,926 at that point before the surplus months bring it back to the net figure.
Funding order
1. Capitalized interest$0
The budget's $2,193,302 of construction interest is drawn by month 24; nothing remains for month 25 on.
2. Lease-up reserve$100,868
The budget's reserve, drawn in full.
3. Sponsor commitment$1,139,132
The remainder, as a GP member loan on the terms below (sample).
- Deficit funded$1,240,000
The sponsor commitment
- Form of the commitment
- GP member loan (sample). Funded by the sponsor as a loan to the partnership, not as equity.
- Priority
- Subordinate to the investor preferred return (sample). Repaid only after investors receive their preferred return.
- Return on it
- 10% simple interest (sample). Accrues from each advance until repaid.
If the lease-up is slower
| Case | Stabilized | Added deficit | Total deficit | Sponsor commitment | Coverage, month 42 test |
|---|---|---|---|---|---|
| Base case | month 36 | $0 | $1,240,000 | $1,139,132 | 1.60x passes |
| 3 months slower | month 39 | $749,142 | $1,989,142 | $1,888,274 | 1.60x passes |
| 6 months slower | month 42 | $1,497,697 | $2,737,697 | $2,636,829 | 1.55x passes |
Base case
- Stabilized
- month 36
- Added deficit
- $0
- Total deficit
- $1,240,000
- Sponsor commitment
- $1,139,132
- Coverage, month 42 test
- 1.60x passes
3 months slower
- Stabilized
- month 39
- Added deficit
- $749,142
- Total deficit
- $1,989,142
- Sponsor commitment
- $1,888,274
- Coverage, month 42 test
- 1.60x passes
6 months slower
- Stabilized
- month 42
- Added deficit
- $1,497,697
- Total deficit
- $2,737,697
- Sponsor commitment
- $2,636,829
- Coverage, month 42 test
- 1.55x passes
Each unit type's fill period stretched by three and six months on the same ramp. Lost income is priced at the lease-up year's own rates per occupied unit; tax and debt service do not move. The first extension test is 1.15x on the trailing 3 months.
Absorption by unit type
| Type | Units | Months to fill | Leases a month, average | Leases, fastest month |
|---|---|---|---|---|
| Studio | 30 | 7 | 4.1 | 7.5 |
| 1BR | 80 | 10 | 7.6 | 14.4 |
| 2BR | 75 | 11 | 6.5 | 12.3 |
| 3BR | 15 | 12 | 1.2 | 2.3 |
Studio
- Units
- 30
- Months to fill
- 7
- Leases a month, average
- 4.1
- Leases, fastest month
- 7.5
1BR
- Units
- 80
- Months to fill
- 10
- Leases a month, average
- 7.6
- Leases, fastest month
- 14.4
2BR
- Units
- 75
- Months to fill
- 11
- Leases a month, average
- 6.5
- Leases, fastest month
- 12.3
3BR
- Units
- 15
- Months to fill
- 12
- Leases a month, average
- 1.2
- Leases, fastest month
- 2.3
Construction debt service in this chart is drawn at a 7.00% all in rate, between today's 5.90% indication and the 7.25% capped maximum. The months below the covenant are real and the funding for them is split three ways: the capitalized interest reserve carries the loan through construction, the lease-up reserve covers part of the operating deficit after delivery, and the balance of that deficit is a sponsor funding commitment, stated with its figures in diligence answer three.
Sponsor track record
Projected vs actual NOI
- Projected NOI
- Actual NOI
| Project | Projected NOI | Actual NOI |
|---|---|---|
| Lake Street Flats | $825,000 | $879,000 |
| Excelsior Commons | $1,512,000 | $1,496,000 |
| Como Avenue Lofts | $608,000 | $631,000 |
| Nicollet Yards | $2,145,000 | $1,983,000 |
| Highland Row | $1,298,000 | $1,314,000 |
| Wayzata Boulevard | $1,980,000 | No actuals yet |
- Lake Street Flats$879,000Third-party verified
- Excelsior Commons$1,496,000Document verified
- Como Avenue Lofts$631,000Document verified
- Nicollet Yards$1,983,000Sponsor reported
- Highland Row$1,314,000Sponsor reported
- Wayzata BoulevardNo actuals yetSponsor reported
| Project | Completed | Units | Projected NOI | Actual NOI | Projected IRR | Realized IRR | Verification | Details |
|---|---|---|---|---|---|---|---|---|
| Lake Street Flats | 2016 | 64 | $825,000 | $879,000 | 16.00% | 18.40% | Third-party verified | |
| Excelsior Commons | 2018 | 112 | $1,512,000 | $1,496,000 | 15.50% | 14.70% | Document verified | |
| Como Avenue Lofts | 2019 | 48 | $608,000 | $631,000 | 15.00% | Not exited | Document verified | |
| Nicollet Yards | 2021 | 156 | $2,145,000 | $1,983,000 | 16.50% | Not exited | Sponsor reported | |
| Highland Row | 2022 | 88 | $1,298,000 | $1,314,000 | 15.50% | Not exited | Sponsor reported | |
| Wayzata Boulevard | 2024 | 132 | $1,980,000 | No actuals yet | 16.00% | Not exited | Sponsor reported |
Lake Street Flats
Minneapolis, 2016
- Market
- Minneapolis
- Completed
- 2016
- Units
- 64
- Total development cost
- $11,840,000
- Projected NOI
- $825,000
- Actual NOI
- $879,000
- Actual vs projected
- +6.5% vs projected
- Projected IRR
- 16.00%
- Realized IRR
- 18.40%
Evidence
- Document
- Audited financial statements
- Reviewed by
- Independent CPA
- Reviewed on
- 2026-09-14
Excelsior Commons
St. Louis Park, 2018
- Market
- St. Louis Park
- Completed
- 2018
- Units
- 112
- Total development cost
- $23,520,000
- Projected NOI
- $1,512,000
- Actual NOI
- $1,496,000
- Actual vs projected
- −1.1% vs projected
- Projected IRR
- 15.50%
- Realized IRR
- 14.70%
Evidence
- Document
- Closing statement and sale HUD
- Reviewed by
- Apolis
- Reviewed on
- 2026-09-20
Como Avenue Lofts
St. Paul, 2019
- Market
- St. Paul
- Completed
- 2019
- Units
- 48
- Total development cost
- $9,120,000
- Projected NOI
- $608,000
- Actual NOI
- $631,000
- Actual vs projected
- +3.8% vs projected
- Projected IRR
- 15.00%
- Realized IRR
- Not exited
Evidence
- Document
- T12 and rent roll
- Reviewed by
- Apolis
- Reviewed on
- 2026-10-02
Nicollet Yards
Richfield, 2021
- Market
- Richfield
- Completed
- 2021
- Units
- 156
- Total development cost
- $34,320,000
- Projected NOI
- $2,145,000
- Actual NOI
- $1,983,000
- Actual vs projected
- −7.5% vs projected
- Projected IRR
- 16.50%
- Realized IRR
- Not exited
Evidence
Sponsor reported. No evidence attached.
Highland Row
St. Paul, 2022
- Market
- St. Paul
- Completed
- 2022
- Units
- 88
- Total development cost
- $20,680,000
- Projected NOI
- $1,298,000
- Actual NOI
- $1,314,000
- Actual vs projected
- +1.2% vs projected
- Projected IRR
- 15.50%
- Realized IRR
- Not exited
Evidence
Sponsor reported. No evidence attached.
Wayzata Boulevard
Golden Valley, 2024
- Market
- Golden Valley
- Completed
- 2024
- Units
- 132
- Total development cost
- $31,680,000
- Projected NOI
- $1,980,000
- Actual NOI
- No actuals yet
- Actual vs projected
- No actuals yet
- Projected IRR
- 16.00%
- Realized IRR
- Not exited
Evidence
Sponsor reported. No evidence attached.
What each verification level means
Sponsor reported until evidence is attached. Document verified when Apolis has reviewed the closing statements or financials. Third-party verified when an independent reviewer has signed the figures. A row the sponsor edits after review reads Sponsor reported again.
Principals, litigation and bankruptcy 2 principals, 2 disclosures
Principals
Principal 1
- Name
- Principal A (sample)
- Role
- Managing member (sample)
- Experience
- 18 years in multifamily development (sample)
- Loan guarantor
- Yes: completion and carve-outs (sample)
Principal 2
- Name
- Principal B (sample)
- Role
- Member, construction and asset management (sample)
- Experience
- 12 years in multifamily construction (sample)
- Loan guarantor
- Yes: completion and carve-outs (sample)
Litigation and bankruptcy
- Litigation involving the sponsor or its principals
- None reported (sample)
- Bankruptcy, foreclosure or deed in lieu
- None reported (sample)
Sponsor fees
Every fee the sponsor earns
Rate, when it is earned, and the ten-year total. Fees not charged are listed at zero.
- Development fee$2,040,000
- Asset management fee$1,462,000
- Promote$7,454,108
| Fee | Rate | Paid from | Ten-year total | Details |
|---|---|---|---|---|
| Development fee | 4.0% | from the budget | $2,040,000 | |
| Asset management fee | 1.0% a year | Operations | $1,462,000 | |
| Promote | 20% to 30% | Distributions | $7,454,108 | |
| Total sponsor compensation over the hold | $10,956,108 |
Development fee
4.0% of total project cost, excluding the fee itself
- Rate
- 4.0%
- Ten-year total
- $2,040,000
- Paid from
- The construction budget
Base
of total project cost, excluding the fee itself
When earned
Earned pro rata over the 24 months of construction, paid from the budget
Asset management fee
1.0% a year of invested equity
- Rate
- 1.0% a year
- Ten-year total
- $1,462,000
- Paid from
- Operations
Base
of invested equity
When earned
Paid quarterly from operations, beginning at first delivery
Promote
20% to 30% of profit, by tier, after capital and preferred return
- Rate
- 20% to 30%
- Ten-year total
- $7,454,108
- Paid from
- Distributions
Base
of profit, by tier, after capital and preferred return
When earned
Earned only at the refinance and the sale, never before
Total sponsor compensation over the hold$10,956,108
Not charged: construction management fee, acquisition fee, guaranty fee, refinance fee, disposition fee.
Who funds each fee
The development fee is 11.2% of the equity being raised, and it is paid from the construction budget rather than from operations, which means investors fund it. Fees paid out of operations across the hold total $1,462,000. The promote is the only one earned after investors have their capital and preferred return back.
Diligence
The ten standard questions
What is the sponsor's experience with this product type in this market?
Diligence question 1 of 10
6 completed mid-rise developments in the Twin Cities, 600 units in aggregate, the most recent delivered 2024. Projected versus actual on each is published on the sponsor profile and marked by verification level.
What is the construction contract and who carries the risk of overrun?
Diligence question 2 of 10
A guaranteed maximum price contract, to be executed with the selected general contractor before closing; the bid package is in progress. The owner's contingency shown in uses is $488,510, which is 1.2% of hard cost: thinner than the 3% to 5% convention on its own, because the sponsor expects the GMP to carry the contractor's own contingency inside it; under it, overruns above the GMP are the contractor's except for owner changes. The two layers together sit inside convention; the owner's layer alone does not, and that is the honest way to read the line.
What are the debt terms and what happens if the deal misses coverage?
Diligence question 3 of 10
Construction loan at 65% of cost, interest-only. Construction-period interest of $2,193,302 is capitalized into basis. The lease-up reserve is $100,868 against a modelled months 25 to 36 deficit of $1,240,000, so the reserve as drawn does not cover it and the $1,139,132 gap is a sponsor commitment whose form has to be stated. The refinance is sized at the binding of maximum loan to value, minimum coverage, and a rate stress.
What is the exit assumption and how sensitive is the return to it?
Diligence question 4 of 10
A 5.50% exit cap on forward twelve-month NOI, 25 basis points above today's market. The sensitivity grid on this page shows the investor return across a 150 basis point band.
How is the lease-up modelled, and what happens if it is slower?
Diligence question 5 of 10
Absorption is set per unit type and occupancy falls out of it rather than being assumed. Eleven months from first delivery (month 25) to stabilization (month 36) in the base case.
What fees does the sponsor earn, and when?
Diligence question 6 of 10
A development fee earned over construction, an asset management fee on invested equity, and a promote earned only after investors receive their preferred return and their capital back.
What is the investor's preferred return and where does it sit?
Diligence question 7 of 10
Investors receive capital back and a preferred return before the sponsor participates in profit beyond its co-investment.
What happens if the deal needs more equity than modelled?
Diligence question 8 of 10
Additional capital is called pro rata. An investor who does not fund is diluted on stated terms set out in the operating agreement, not at the sponsor's discretion.
Who holds the money and who signs the loan?
Diligence question 9 of 10
The project entity holds all funds at a named bank. The sponsor principals carry completion and standard carve-out guarantees.
What reporting will an investor receive after closing?
Diligence question 10 of 10
Quarterly statements from the same record that produced this page: capital account, distributions to date, actual against projected operations, and loan balances. K-1s are posted to the deal room, never prepared by Apolis. The sponsor targets K-1 delivery by March 15; timing depends on the partnership's tax filing.
The project team 6 roles, sample names in the live format
Each status restates a fact shown elsewhere: the GMP in diligence two, the signed term sheet in the debt terms, the appeal period in the schedule.
Sponsor and developer
Sample Sponsor LLC
6 completed developments, record above, co-invested pari passu
General contractor
Sample Builders Co
Bid package in progress; guaranteed maximum price to be executed before closing, contingency inside the GMP
Architect
Sample Architecture Studio
Schematic design under way, construction administration through delivery
Construction lender
Sample Regional Bank
Term sheet signed, in-balance tested at each draw
Property manager
Sample Residential Management
Engaged for pre-leasing at first delivery and operations after
Counsel
Sample Law LLP
Entitlements through the expired appeal period, loan and equity closings
Data room index Every document, the tier that opens it, and its status.
Data room index
What opens at each tier. Statuses are sample statuses; the live index updates as the sponsor uploads, and every view and download is logged.
- Teaser
- Every invited investor
- Full materials
- After accreditation attestation and the sponsor's confidentiality terms
- Closed investors
- Investors who have closed
Entitlement approvals
- Tier
- Teaser
- Status
- Available
- Schema kind
- No schema kind yet
Offering memorandum
- Tier
- Full materials
- Status
- Available
- Schema kind
- om
Development budget
- Tier
- Full materials
- Status
- Available
- Schema kind
- budget
GMP construction contract
- Tier
- Full materials
- Status
- Pending
- Schema kind
- No schema kind yet
To be executed before closing; the bid package is in progress
Construction loan term sheet
- Tier
- Full materials
- Status
- Available
- Schema kind
- loan_term_sheet
Appraisal
- Tier
- Full materials
- Status
- Pending
- Schema kind
- No schema kind yet
Geotechnical report
- Tier
- Full materials
- Status
- Not started
- Schema kind
- No schema kind yet
Not started, per the bid package's owner documents
Phase I environmental site assessment
- Tier
- Full materials
- Status
- Available
- Schema kind
- No schema kind yet
Received, per the bid package's owner documents
ALTA survey
- Tier
- Full materials
- Status
- Pending
- Schema kind
- No schema kind yet
Pending, per the bid package's owner documents
Title commitment
- Tier
- Full materials
- Status
- Available
- Schema kind
- No schema kind yet
Received, per the bid package's owner documents
Rent roll
- Tier
- Full materials
- Status
- Not applicable
- Schema kind
- rent_roll
Ground-up: no existing tenants
Trailing twelve months (T12)
- Tier
- Full materials
- Status
- Not applicable
- Schema kind
- t12
Ground-up: no operating history
Subscription documents
- Tier
- Closed investors
- Status
- Pending
- Schema kind
- sub_doc
| Document | Tier | Status (sample) | Schema kind |
|---|---|---|---|
| Entitlement approvals | Teaser | Available | No schema kind yet |
| Offering memorandum | Full materials | Available | om |
| Development budget | Full materials | Available | budget |
| GMP construction contractTo be executed before closing; the bid package is in progress | Full materials | Pending | No schema kind yet |
| Construction loan term sheet | Full materials | Available | loan_term_sheet |
| Appraisal | Full materials | Pending | No schema kind yet |
| Geotechnical reportNot started, per the bid package's owner documents | Full materials | Not started | No schema kind yet |
| Phase I environmental site assessmentReceived, per the bid package's owner documents | Full materials | Available | No schema kind yet |
| ALTA surveyPending, per the bid package's owner documents | Full materials | Pending | No schema kind yet |
| Title commitmentReceived, per the bid package's owner documents | Full materials | Available | No schema kind yet |
| Rent rollGround-up: no existing tenants | Full materials | Not applicable | rent_roll |
| Trailing twelve months (T12)Ground-up: no operating history | Full materials | Not applicable | t12 |
| Subscription documents | Closed investors | Pending | sub_doc |
Investor questions
11 answered, visible to all invited investors
Sponsor's answer
The sponsor targets K-1 delivery by March 15; timing depends on the partnership's tax filing. The partnership's outside accountant prepares them and each investor downloads their own; Apolis delivers K-1s and does not prepare them. Quarterly statements come from the same record as this page, as diligence answer 10 describes: capital account, distributions to date, actual against projected operations, and loan balances.
Asked by an invited investor on Nov 6, 2026. Answered by the sponsor on Nov 7, 2026. Visible to all invited investors.
Sponsor's answer
The sponsor expects a GMP contract; under it, overruns above the GMP are the contractor's except for owner changes. The sponsor expects to sign it with the selected general contractor before closing; the bid package is out now, and until it is signed, overrun risk sits with the partnership. The owner's contingency in the uses is $488,510, 1.2% of the $41.0M hard cost. On its own that layer is thin by convention; under the expected contract the contractor's own contingency sits inside the GMP, and diligence answer 2 reads the two layers together.
Asked by an invited investor on Oct 16, 2026. Answered by the sponsor on Nov 5, 2026. Visible to all invited investors.
Sponsor's answer
Market concession observed: 4.33 weeks median across 3 of 4 properties; the pro forma carries 0.5% of gross potential rent (0.26 weeks on a 12-month lease) at stabilization and none in lease-up. The rent comparison in section five shows each unit type's pro forma rent against posted asks and, where a property posts a concession, the effective median after it, with each posted base-rent concession spread over a 12-month lease. Asks are not effective rents, and the concession rate is the sponsor's input.
Asked by an invited investor on Nov 3, 2026. Answered by the sponsor on Nov 4, 2026. Visible to all invited investors.
Investor questions
11 answered, visible to all invited investors
Asked on this page by invited investors and answered once by the sponsor. Askers are not named. Where an answer concerns a model assumption, the link opens the section where that assumption is shown.
11 questions
Sponsor's answer
The sponsor targets K-1 delivery by March 15; timing depends on the partnership's tax filing. The partnership's outside accountant prepares them and each investor downloads their own; Apolis delivers K-1s and does not prepare them. Quarterly statements come from the same record as this page, as diligence answer 10 describes: capital account, distributions to date, actual against projected operations, and loan balances.
Asked by an invited investor on Nov 6, 2026. Answered by the sponsor on Nov 7, 2026. Visible to all invited investors.
Sponsor's answer
The sponsor expects a GMP contract; under it, overruns above the GMP are the contractor's except for owner changes. The sponsor expects to sign it with the selected general contractor before closing; the bid package is out now, and until it is signed, overrun risk sits with the partnership. The owner's contingency in the uses is $488,510, 1.2% of the $41.0M hard cost. On its own that layer is thin by convention; under the expected contract the contractor's own contingency sits inside the GMP, and diligence answer 2 reads the two layers together.
Asked by an invited investor on Oct 16, 2026. Answered by the sponsor on Nov 5, 2026. Visible to all invited investors.
Sponsor's answer
Market concession observed: 4.33 weeks median across 3 of 4 properties; the pro forma carries 0.5% of gross potential rent (0.26 weeks on a 12-month lease) at stabilization and none in lease-up. The rent comparison in section five shows each unit type's pro forma rent against posted asks and, where a property posts a concession, the effective median after it, with each posted base-rent concession spread over a 12-month lease. Asks are not effective rents, and the concession rate is the sponsor's input.
Asked by an invited investor on Nov 3, 2026. Answered by the sponsor on Nov 4, 2026. Visible to all invited investors.
Sponsor's answer
The preferred return is 8% a year on unreturned capital. It accrues from the date capital is funded and compounds annually. Unpaid preferred return rolls forward rather than lapsing, so a year without a distribution is deferred, not forgiven. Capital comes back in tier two, and the month 61 refinance is the first event large enough to return it. The sponsor's catch-up splits 50/50. The projected investor IRR of 15.16% sits just above the 15% hurdle, so most of the promote is earned in tier four at 80/20, and nothing is distributed in tier five in the base case.
Asked by an invited investor on Oct 31, 2026. Answered by the sponsor on Nov 1, 2026. Visible to all invited investors.
Sponsor's answer
Three. A development fee of 4.0% of total project cost, excluding the fee itself, $2,040,000: earned pro rata over the 24 months of construction, paid from the budget. An asset management fee of 1.0% a year of invested equity, $1,462,000 over the hold: paid quarterly from operations, beginning at first delivery. The promote, 20% to 30% of profit, by tier, after capital and preferred return, $7,454,108 in the base case: earned only at the refinance and the sale, never before. No construction management, acquisition, guaranty, refinance or disposition fee is charged.
Asked by an invited investor on Oct 29, 2026. Answered by the sponsor on Oct 30, 2026. Visible to all invited investors.
Sponsor's answer
The sponsor invests $548K, 3.0% of the $18.3M of equity, pari passu with investors. The promote, $7,454,108 in the base case, opens only after investors receive their 8% preferred return and all contributed capital, and a clawback is tested at final liquidation. The sponsor principals also carry the construction loan's completion guarantee and standard carve-outs, with no guaranty fee.
Asked by an invited investor on Oct 26, 2026. Answered by the sponsor on Oct 27, 2026. Visible to all invited investors.
Sponsor's answer
The sale in month 120 is priced at a 5.50% cap on forward twelve-month NOI, a price of $80.0M. After the permanent loan is repaid, net sale proceeds to equity are $35.1M. The grid in section eight crosses the exit cap with market rent and shows the investor IRR in each cell against an illustrative 12% allocator screen.
Asked by an invited investor on Oct 23, 2026. Answered by the sponsor on Oct 25, 2026. Visible to all invited investors.
Sponsor's answer
Directly. The permanent loan is assumed at 5.40% fixed. That is a forecast, not a commitment, and no permanent lender is engaged. The loan is sized at the lowest of three tests, and minimum debt service coverage binds at $47.0M, which pays off $33.0M of construction debt and distributes $14.0M. Sized on the same coverage test at a 7.15% stress rate, the loan would be $39.0M. At 6.50% instead the loan sizes to roughly $41.6M and the month 61 distribution falls from $14.0M to about $8.6M. The construction loan is floating, at SOFR plus 275 basis points, with a purchased cap at 4.50%. Underwritten at 7.00% all in: the cash flow's construction debt service is drawn at that rate, above today's 5.90% indication and below the 7.25% capped maximum.
Asked by an invited investor on Oct 21, 2026. Answered by the sponsor on Oct 22, 2026. Visible to all invited investors.
Sponsor's answer
Yes. Base case requires both extensions (months 42 and 54). The initial term ends at month 42 and the refinance is modelled in month 61. Extension one is exercised at month 42 for a 25 basis point fee on $33,922,221 outstanding, $84,806, with projected trailing coverage of 1.60x against the lender's 1.15x test, which passes. Extension two is exercised at month 54 for a 25 basis point fee on $33,922,221 outstanding, $84,806, with projected trailing coverage of 1.64x against the lender's 1.15x test, which passes. Fully extended, the loan matures at month 66, five months after the modelled refinance. The extension fees, $169,611 together, are not in the cash flow or the uses.
Asked by an invited investor on Oct 19, 2026. Answered by the sponsor on Oct 20, 2026. Visible to all invited investors.
Sponsor's answer
In order: capitalized interest first, which the draw schedule spends by month 24, so $0 of it remains for lease-up; the lease-up reserve next, drawn in full at $100,868; and the remaining $1,139,132 is a sponsor commitment. None of it is investor capital. The running shortfall peaks at $1,474,794 in month 32, so the commitment has to be available for $1,373,926 at that point, before surplus months from month 33 pay part of it back. Its terms, shown in section eight: GP member loan, subordinate to the investor preferred return, 10% simple interest (sample).
Asked by an invited investor on Oct 14, 2026. Answered by the sponsor on Oct 15, 2026. Visible to all invited investors.
Sponsor's answer
Absorption is set per unit type rather than as one building pace, measured from first delivery in month 25: studios in 7 months, 1BR in 10 months, 2BR in 11 months and 3BR in 12 months. The slowest plan sets stabilization at month 36. The slower lease-up table in section eight runs the same ramp three and six months slower: stabilization moves to month 39 and month 42, and the lease-up deficit grows by $749,142 and $1,497,697. Projected coverage at the first construction loan extension test is 1.60x and 1.55x against a 1.15x test, so the test passes in both.
Asked by an invited investor on Oct 12, 2026. Answered by the sponsor on Oct 13, 2026. Visible to all invited investors.