Deal: St. Louis Park West End, 200 unitsPage: Projected vs actual

Projected vs actual

Sample

Each deal against its plan: dates, spend, lease-up and NOI.

Sample deals and figures, as of Nov 7, 2026.

Milestones on time
38.9%
11 late7 of 18 milestones
Median days late
5
Across 11 late milestones
Budget variance
+2.4%
+$4,342,9225 deals with a budget comparison
NOI vs plan ยท trailing twelve months
97.3%
Below plan1 operating deal
Milestones, planned against actual or forecast Planned Actual Forecast
  1. Illustrative: 200-unit multifamily development: First look
  2. Illustrative: 200-unit multifamily development: Letter of intent
  3. Illustrative: 200-unit multifamily development: Purchase agreement
  4. Illustrative: 200-unit multifamily development: Site control
  5. Illustrative: 200-unit multifamily development: Survey and Phase I
  6. Illustrative: 200-unit multifamily development: Due diligence
  7. Illustrative: 200-unit multifamily development: Entitlements and city approvals
  8. Illustrative: 200-unit multifamily development: Design: schematic design
  9. Illustrative: 200-unit multifamily development: Design: design development
  10. Illustrative: 200-unit multifamily development: Design: construction documents
  11. Illustrative: 200-unit multifamily development: GC bids
  12. Illustrative: 200-unit multifamily development: Loan term sheet
  13. Illustrative: 200-unit multifamily development: GC award and GMP contract
  14. Illustrative: 200-unit multifamily development: Loan commitment
  15. Illustrative: 200-unit multifamily development: Equity raise
  16. Illustrative: 200-unit multifamily development: Closing
  17. Cedar Lake flats: Construction complete
  18. Hiawatha yards: Construction complete
Aug 9, 2025As of Nov 7, 2026Oct 9, 2027

Where each deal stands against plan

  • Illustrative: 200-unit multifamily development
  • East Bank mill
  • Wedge triangle
  • Cedar Lake flats
  • Hiawatha yards
  • Lowry flats
  • Nicollet commons
  • Minnehaha lofts
Sources and method
  • Deal schedule (src/lib/deal-schedule.ts)
  • Construction health inputs (src/lib/pipeline-sample-board.ts)
  • Budget estimates (src/lib/sample-portfolio.ts)
  • Lease-up status (src/lib/sample-portfolio.ts)
  • Operating status, trailing twelve months (src/lib/sample-portfolio.ts)
  • REO schedule (src/lib/sample-reo.ts)
  • On time means the actual or forecast finish is on or before the planned date. Median days late counts late milestones only.
  • Budget variance sums each deal's current figure against its budget; bases differ by deal and are stated in each row.
  • A blank comparison means no sample record holds the figure. Nothing is filled in.