Timeline
By right, 14 months from site control to close. Current phase: Financing and closing.
1. Site control2 mo
Complete- Gate
- Purchase agreement executed, diligence period open
- Owner
- Counsel
2. Feasibility2 mo
Complete- Gate
- Untrended yield on cost clears the screen
- Owner
- Sponsor
3. Design to permit set5 mo
Complete- Gate
- Building permit application filed
- Owner
- Architect
4. Permitting3 mo
Complete- Gate
- Building permit issued
- Owner
- City
5. Financing and closing2 mo
Current phase- Gate
- Loan and equity close the same day as land
- Owner
- Sponsor
Today's zoning carries the count. The city is a plan reviewer, not a vote. Months are the phase's illustrative default.
Tasks for Raising
0 of 7 closed. Stage entered Oct 26. Sample team.
- Loan request packageDue Nov 9
Capital
- GC award and GMP contractDue Nov 16
Construction managerGates the stage
- Loan commitmentDue Nov 20
CapitalGates the stage
- Signed term sheetDue Dec 10
CapitalGates the stage
- Equity raise committedDue Jan 24
CapitalGates the stage
- AppraisalDue Dec 25
Analyst
- Closing checklist completeDue Feb 13
LegalGates the stage
Gate review: leaving Raising
0 of 2 partners have decided. Moving forward without approval shows a warning. Sample partners. Decisions are never edited; a change is a new entry.
- Sample Dana OrtizPendingNot yet decided
- Sample Marcus LeePendingNot yet decided
- Name
- Sample site: Aspen Court Apartments
- Stage
- Raising
- Units
- 118
- Strategy
- Ground-up
- Zoning path
- By right
- Estimated total development cost
- $33,800,000
- Waiting on
- Construction term sheet countersigned
- Gate due
- Dec 2026
- Gate owner
- Sponsor
- Days in stage
- 12
- Note
- Underwriting lives in the listing builder; the deal page publishes from it when the debt signs.
- Working surface
- Open the underwriting
- Location
- Lowry Hill East (the Wedge) (neighborhood centroid 44.955, -93.293)
- Drawing state
- Illustrative massing
- Drawing required at the feasibility gate
- Illustrative massing. Architect set: not uploaded · Architect
- Typology
- 4-over-1 podium, 5 stories, about 30 units per residential floor (from the rule)
- Shows the unit count at a stated typology, not what fits on the site. Site acreage, zoning height and parking ratio not yet entered.
Illustrative massing, not an architect's drawing
Unit count at 4-over-1 podium (by rule), not site fit.
Developer notes
Sample contractor · Oct 25, 2026
GMP landed inside the budget band. Contingency held at the level in the listing builder.
Sample sponsor · Nov 1, 2026
Two lender term sheets in hand. The one we prefer sizes on cost, not value, which keeps the equity check where the listing shows it.
Documents
- Sample permit set drawingsDrawings · Sep 28, 2026
- Sample guaranteed maximum priceBudget · Oct 25, 2026
- Sample construction loan term sheetLoan term sheet · Nov 1, 2026
Names only. Sample records carry no files.
Change log
- Oct 26, 2026Sample contractorOwnerGC changed to Sponsor
- Oct 26, 2026Sample sponsorGateGMP within 3% of budget changed to Construction term sheet countersigned
- Oct 26, 2026Sample sponsorStageDesign and pricing changed to Raising
- Jun 20, 2026Sample sponsorStageFeasibility changed to Design and pricing
- Apr 6, 2026Sample sponsorStageSourcing changed to Feasibility
- Feb 20, 2026Sample sponsorStageNot tracked changed to Sourcing