Timeline
Rezone, 23 months from site control to close. Current phase: Site control.
1. Site control3 mo
Current phase- Gate
- Purchase agreement executed with entitlement contingency
- Owner
- Counsel
2. Feasibility2 mo
Ahead- Gate
- Untrended yield on cost clears the screen at the proposed count
- Owner
- Sponsor
3. Neighborhood and city pre-application2 mo
Ahead- Gate
- Staff report favorable
- Owner
- Sponsor
4. Rezoning and site plan6 mo
Ahead- Gate
- Council approval recorded
- Owner
- City
5. Appeal period1 mo
Ahead- Gate
- Expired without challenge
- Owner
- Counsel
6. Design to permit set4 mo
Ahead- Gate
- Building permit application filed
- Owner
- Architect
7. Permitting3 mo
Ahead- Gate
- Building permit issued
- Owner
- City
8. Financing and closing2 mo
Ahead- Gate
- Loan and equity close the same day as land
- Owner
- Sponsor
Today's zoning does not carry the count. The public path governs the clock. Months are the phase's illustrative default.
Tasks for Sourcing
5 of 5 closed. Stage entered Oct 7. Sample team.
- Site visitDue Oct 14
Development lead
- Broker callDue Oct 14
Development lead
- Zoning checkDue Oct 21
AnalystGates the stage
- Run the screenDue Oct 28
AnalystGates the stage
- Letter of intentDue Nov 6
Legal
- Name
- Sample site: Larkspur Flats
- Stage
- Sourcing
- Units
- 210
- Strategy
- Ground-up
- Zoning path
- Rezone
- Estimated total development cost
- $58,000,000
- Waiting on
- Phase one environmental back
- Gate due
- Dec 2026
- Gate owner
- Counsel
- Days in stage
- 31
- Note
- Former light industrial. The price works only if the cap on remediation holds.
- Working surface
- None yet
- Location
- Northeast Minneapolis, arts district (neighborhood centroid 45.004, -93.259)
- Drawing state
- Not due until feasibility
- Drawing required at the feasibility gate
- Not due until feasibility · Architect
- Shows the unit count at a stated typology, not what fits on the site. Site acreage, zoning height and parking ratio not yet entered.
No drawing is due before the feasibility gate.
Developer notes
Sample sponsor · Oct 8, 2026
Former light industrial use. The price only works if the seller caps our remediation exposure, so the environmental read comes before anything else.
Sample counsel · Oct 26, 2026
Historical use review shows a former plating shop on the north half. Phase I consultant expects a recommendation for limited Phase II sampling.
Documents
- Sample letter of intent, countersignedLetter of intent · Oct 17, 2026
- Sample Phase I proposalEnvironmental · Oct 19, 2026
- Sample historical use summaryEnvironmental · Oct 26, 2026
Names only. Sample records carry no files.
Change log
- Oct 18, 2026Sample counselGateLetter of intent countersigned changed to Phase one environmental back
- Oct 11, 2026Sample sponsorOwnerSponsor changed to Counsel
- Oct 7, 2026Sample sponsorStageNot tracked changed to Sourcing