Timeline
By right, 14 months from site control to close. Current phase: Design to permit set.
1. Site control2 mo
Complete- Gate
- Purchase agreement executed, diligence period open
- Owner
- Counsel
2. Feasibility2 mo
Complete- Gate
- Untrended yield on cost clears the screen
- Owner
- Sponsor
3. Design to permit set5 mo
Current phase- Gate
- Building permit application filed
- Owner
- Architect
4. Permitting3 mo
Ahead- Gate
- Building permit issued
- Owner
- City
5. Financing and closing2 mo
Ahead- Gate
- Loan and equity close the same day as land
- Owner
- Sponsor
Today's zoning carries the count. The city is a plan reviewer, not a vote. Months are the phase's illustrative default.
Tasks for Design and pricing
0 of 5 closed. Stage entered Sep 27. Sample team.
- Schematic design setDue Nov 11
Construction manager
- Design development setDue Jan 10
Construction manager
- Construction document setDue Mar 26
Construction managerGates the stage
- GC preconstruction and pricingDue Jan 25
Construction managerGates the stage
- Building permit submittalDue Apr 5
Development lead
Gate review: leaving Design and pricing
0 of 2 partners have decided. Moving forward without approval shows a warning. Sample partners. Decisions are never edited; a change is a new entry.
- Sample Dana OrtizPendingNot yet decided
- Sample Marcus LeePendingNot yet decided
- Name
- Sample site: Stonegate Lofts
- Stage
- Design and pricing
- Units
- 164
- Strategy
- Value-add
- Zoning path
- By right
- Estimated total development cost
- $38,900,000
- Waiting on
- GMP within 3% of budget
- Gate due
- Jan 2027
- Gate owner
- GC
- Days in stage
- 41
- Note
- Occupied renovation in phases. The lease engine question, which units turn when, is the whole deal.
- Working surface
- None yet
- Location
- St. Anthony Main, east bank (neighborhood centroid 44.986, -93.254)
- Drawing state
- Illustrative massing
- Drawing required at the feasibility gate
- Illustrative massing. Architect set: not uploaded · Architect
- Typology
- 5-over-1 podium, 6 stories, about 33 units per residential floor (from the rule)
- Shows the unit count at a stated typology, not what fits on the site. Site acreage, zoning height and parking ratio not yet entered. Existing building: the block stands in for an as-built survey and shows the unit count only.
Illustrative massing, not an architect's drawing
Unit count at 5-over-1 podium (by rule), not site fit.
Developer notes
Sample architect · Sep 30, 2026
As-built survey complete. Two of the four floors carry the original timber frame, which limits where new risers can run.
Sample contractor · Oct 23, 2026
Pricing slipped a month while the phasing plan was settled. The occupied turns drive the general conditions line.
Sample sponsor · Nov 3, 2026
Which units turn in which quarter is the whole deal here. Holding the GMP review until the turn schedule is fixed.
Documents
- Sample as-built surveySurvey · Sep 30, 2026
- Sample rent roll, currentRent roll · Oct 8, 2026
- Sample renovation phasing planDrawings · Oct 20, 2026
Names only. Sample records carry no files.
Change log
- Oct 23, 2026Sample contractorGate dueDec 2026 changed to Jan 2027
- Sep 27, 2026Sample sponsorOwnerSponsor changed to GC
- Sep 27, 2026Sample sponsorStageFeasibility changed to Design and pricing
- Jun 10, 2026Sample sponsorStageSourcing changed to Feasibility
- Apr 21, 2026Sample sponsorStageNot tracked changed to Sourcing